9106 W MONTE MAR DR 90035

Certificate Information: 9106 W MONTE MAR DR 90035

Application / Permit
19014-70000-05167
Plan Check / Job No.
B19SL01293
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 17'1"x21'2"ADDITION AT REAR AND 20'4"x15'11" AND 1'11"X16'3" ADDITIONS AT FRONT TO (E) SINGLE FAMILY DWELLING PER ENGINEER
Permit Issued
Issued on 12/10/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/19/2019 APPLICANT
Green Plans Picked Up 10/2/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 GEORGE ALVAREZ
Corrections Issued 10/7/2019 GEORGE ALVAREZ
Quality Review Completed 10/12/2019 STANLEY RAAP
Building Plans Picked Up 10/18/2019 APPLICANT
Plan Check Approved 12/10/2019 GEORGE ALVAREZ
No Progress 12/10/2019 GEORGE ALVAREZ
Plan Check Approved 12/10/2019 GEORGE ALVAREZ
Issued 12/10/2019 LADBS
CofO in Progress 7/15/2021 KEVIN SARGSYAN
Permit Finaled 7/30/2021 KENNETH NAGLE
CofO Issued 7/30/2021 KENNETH NAGLE
Permit Finaled 7/30/2021 KENNETH NAGLE

Permit Application Clearance Information

Green Code Cleared 10/15/2019 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/21/2019 THAN WIN
Sewer availability Cleared 11/21/2019 THAN WIN
Grading Pre-Inspection Cleared 11/25/2019 PATRICK MISCHLICH
Low Impact Development Cleared 11/26/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/26/2019 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/24/2020 Conditional Approval RONALD WEBER
Excavation/Setback/Form/Re-Bar 1/29/2020 Approved RONALD WEBER
Footing/Foundation/Slab 1/29/2020 Conditional Approval RONALD WEBER
Pre-Inspection 1/29/2020 Partial Inspection RONALD WEBER
BUILDING-Rough-Frame 2/7/2020 Partial Approval RONALD WEBER
Footing/Foundation/Slab 2/7/2020 Conditional Approval RONALD WEBER
METHANE-Barrier 2/7/2020 Not Ready for Inspection RONALD WEBER
METHANE-Subgrade 2/7/2020 Not Ready for Inspection RONALD WEBER
BUILDING-Rough-Frame 4/6/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/6/2020 Partial Approval EVAN COOPER
Green Building Rough 4/6/2020 Not Ready for Inspection EVAN COOPER
METHANE-Final 4/6/2020 Partial Approval EVAN COOPER
METHANE-Rough 4/6/2020 Approved EVAN COOPER
Structural Steel Frame 4/6/2020 Partial Approval EVAN COOPER
Wood Frame 4/6/2020 Partial Approval EVAN COOPER
ELECTRICAL-Rough 4/22/2020 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 4/22/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/22/2020 Approved GERMAN RODRIGUEZ MENDOZA
Sewer 4/22/2020 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/30/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 4/30/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 4/30/2020 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 5/7/2020 Partial Inspection CRAIG DAVIS
Green Building Rough 5/7/2020 Not Ready for Inspection CRAIG DAVIS
METHANE-Rough 5/7/2020 Not Ready for Inspection CRAIG DAVIS
Insulation 6/2/2020 Approved CRAIG DAVIS
Interior/Exterior Lathing 6/2/2020 Partial Approval CRAIG DAVIS
Drywall Nailing 6/15/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 6/15/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 10/19/2020 Corrections Issued KEVIN SARGSYAN
Smoke Detectors 10/19/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 10/21/2020 Approved KEVIN SARGSYAN
PLUMBING-Final 11/5/2020 Approved KEVIN SARGSYAN
HVAC-Final 6/14/2021 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 7/15/2021 Approved KEVIN SARGSYAN
Final 7/15/2021 OK to Issue CofO KEVIN SARGSYAN
Footing/Foundation/Slab 7/15/2021 Approved KEVIN SARGSYAN
Green Building Final 7/15/2021 Approved KEVIN SARGSYAN
Green Building Rough 7/15/2021 Approved KEVIN SARGSYAN
HVAC-Final 7/15/2021 Approved KEVIN SARGSYAN
METHANE-Barrier 7/15/2021 Approved KEVIN SARGSYAN
METHANE-Final 7/15/2021 Approved KEVIN SARGSYAN
METHANE-Rough 7/15/2021 Approved KEVIN SARGSYAN
METHANE-Subgrade 7/15/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/15/2021 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 7/15/2021 Approved KEVIN SARGSYAN