647 1/2 W 111TH PL 90044

Certificate Information: 647 1/2 W 111TH PL 90044

Application / Permit
19014-70000-05058
Plan Check / Job No.
B19SL01257
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2 STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 ATTACHED TO (E) GARAGE
Permit Issued
Issued on 5/12/2022
Issuing Office
Current Status
CofO Issued on 2/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 SAMUEL GONZALEZ
Corrections Issued 10/11/2019 SAMUEL GONZALEZ
Quality Review Completed 10/24/2019 QUAN NGHIEM
Green Plans Picked Up 11/7/2019 APPLICANT
Plan Check Approved 5/10/2022 SAMUEL GONZALEZ
Issued 5/12/2022 APPLICANT
Building Plans Picked Up 5/18/2022 APPLICANT
CofO in Progress 1/19/2023 JAMES CHAVEZ
CofO in Progress 1/19/2023 JAMES CHAVEZ
CofO in Progress 1/24/2023 JAMES CHAVEZ
Permit Finaled 2/7/2023 ANSON MAGLASANG
CofO Issued 2/7/2023 ANSON MAGLASANG
Permit Finaled 2/7/2023 ANSON MAGLASANG

Permit Application Clearance Information

Green Code Cleared 1/24/2020 KHEDER ALRAZAA
Address approval Cleared 7/29/2020 JEANIE LAM
Construction near power lines Cleared 11/8/2021 RIDWAN HARDY
Low Impact Development Cleared 2/1/2022 MITESH PATEL
Community Plan Implem. Overlay Cleared 2/10/2022 RAFAEL FONTES
Eng Process Fee Ord 176,300 Cleared 2/11/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 2/11/2022 TREVOR QUAN
Sewer availability Cleared 2/14/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/16/2022 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 7/18/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/23/2022 Corrections Issued EUGENE CASSIDY
Green Building Rough 8/23/2022 Not Ready for Inspection EUGENE CASSIDY
Deputy Wood Construction 8/25/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 9/1/2022 Partial Approval RYAN SALAZAR
Green Building Rough 9/1/2022 Not Ready for Inspection RYAN SALAZAR
BUILDING-Rough-Frame 9/29/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/29/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 9/29/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 9/29/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 9/29/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 10/4/2022 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Approved ALIZAH MAYAGOITIA
HVAC-Rough 10/4/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 10/4/2022 Approved ALIZAH MAYAGOITIA
Underground Mechanical 10/4/2022 Approved ALIZAH MAYAGOITIA
Insulation 10/20/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/20/2022 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 11/2/2022 Approved JOHN KLARIN
Green Building Rough 11/2/2022 Approved JOHN KLARIN
ELECTRICAL-Final 12/23/2022 Partial Inspection JAMES CHAVEZ
Final 12/23/2022 Not Ready for Inspection JAMES CHAVEZ
Green Building Final 12/23/2022 Not Ready for Inspection JAMES CHAVEZ
HVAC-Final 12/23/2022 Approved JAMES CHAVEZ
PLUMBING-Final 12/23/2022 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 12/23/2022 SGSOV Not Ready JAMES CHAVEZ
Service/Power Release 12/23/2022 Approved JAMES CHAVEZ
Smoke Detectors 12/23/2022 Corrections Issued JAMES CHAVEZ
Final 12/30/2022 OK to Issue CofO JAMES CHAVEZ
Green Building Final 12/30/2022 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 12/30/2022 SGSOV Approved JAMES CHAVEZ
Smoke Detectors 12/30/2022 Approved JAMES CHAVEZ