647 1/2 W 111TH PL 90044
Certificate Information: 647 1/2 W 111TH PL 90044
- Application / Permit
- 19014-70000-05058
- Plan Check / Job No.
- B19SL01257
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2 STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 ATTACHED TO (E) GARAGE
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2019 | SAMUEL GONZALEZ |
| Corrections Issued | 10/11/2019 | SAMUEL GONZALEZ |
| Quality Review Completed | 10/24/2019 | QUAN NGHIEM |
| Green Plans Picked Up | 11/7/2019 | APPLICANT |
| Plan Check Approved | 5/10/2022 | SAMUEL GONZALEZ |
| Issued | 5/12/2022 | APPLICANT |
| Building Plans Picked Up | 5/18/2022 | APPLICANT |
| CofO in Progress | 1/19/2023 | JAMES CHAVEZ |
| CofO in Progress | 1/19/2023 | JAMES CHAVEZ |
| CofO in Progress | 1/24/2023 | JAMES CHAVEZ |
| Permit Finaled | 2/7/2023 | ANSON MAGLASANG |
| CofO Issued | 2/7/2023 | ANSON MAGLASANG |
| Permit Finaled | 2/7/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Green Code | Cleared | 1/24/2020 | KHEDER ALRAZAA |
| Address approval | Cleared | 7/29/2020 | JEANIE LAM |
| Construction near power lines | Cleared | 11/8/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/1/2022 | MITESH PATEL |
| Community Plan Implem. Overlay | Cleared | 2/10/2022 | RAFAEL FONTES |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 2/11/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 2/14/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/16/2022 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 7/18/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/23/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Deputy Wood Construction | 8/25/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/1/2022 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 9/1/2022 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 9/29/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 9/29/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 9/29/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/29/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/4/2022 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/4/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 10/4/2022 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 10/4/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 10/20/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/20/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 11/2/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 11/2/2022 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 12/23/2022 | Partial Inspection | JAMES CHAVEZ |
| Final | 12/23/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| Green Building Final | 12/23/2022 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Final | 12/23/2022 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 12/23/2022 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Not Ready | JAMES CHAVEZ |
| Service/Power Release | 12/23/2022 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 12/23/2022 | Corrections Issued | JAMES CHAVEZ |
| Final | 12/30/2022 | OK to Issue CofO | JAMES CHAVEZ |
| Green Building Final | 12/30/2022 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Approved | JAMES CHAVEZ |
| Smoke Detectors | 12/30/2022 | Approved | JAMES CHAVEZ |