848-848 1/2 W 68TH ST 90044

Certificate Information: 848-848 1/2 W 68TH ST 90044

Application / Permit
19014-70000-04919
Plan Check / Job No.
B19SL01219
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADDITION AND CONVERSION OF (E) SINGLE FAMILY DWELLING AT REAR OF LOT INTO A DUPLEX
Permit Issued
Issued on 1/29/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 ARMEN JIVALAGIAN
Corrections Issued 9/25/2019 ARMEN JIVALAGIAN
Quality Review Completed 10/2/2019 TIEN JEN WANG
Building Plans Picked Up 10/11/2019 APPLICANT
Applicant returned to address corrections 1/3/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 1/9/2020 ARMEN JIVALAGIAN
Plan Check Approved 1/24/2020 ARMEN JIVALAGIAN
No Progress 1/24/2020 ARMEN JIVALAGIAN
Plan Check Approved 1/24/2020 ARMEN JIVALAGIAN
Issued 1/29/2020 LADBS
CofO in Progress 8/18/2020 COREY HUPP
CofO in Progress 8/18/2020 COREY HUPP
Permit Finaled 9/3/2020 DEROLD HAUFF
CofO Issued 9/3/2020 DEROLD HAUFF
Permit Finaled 9/3/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/17/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 12/17/2019 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 12/17/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/17/2019 EMIL KYUPELYAN
ZI Cleared 12/17/2019 JASON CHAN
Green Code Cleared 12/27/2019 SARAH ABOULHOSN

Contact Information

Contractor Largo Construction Inc; Lic. No.: 1011935-B 5864 EAST RANCHO DRIVE      FRESNO, CA 93727
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2020 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 2/18/2020 Corrections Issued EUGENE CASSIDY
Wood Frame 2/18/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 4/22/2020 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/28/2020 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/30/2020 Partial Inspection EUGENE CASSIDY
PLUMBING-Rough 4/30/2020 Corrections Issued EUGENE CASSIDY
Wood Frame 4/30/2020 Corrections Issued EUGENE CASSIDY
Insulation 5/6/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 5/6/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/8/2020 Partial Approval EUGENE CASSIDY
Drywall Nailing 5/8/2020 Partial Approval EUGENE CASSIDY
Green Building Rough 5/8/2020 Partial Approval EUGENE CASSIDY
Wood Frame 5/8/2020 Partial Approval EUGENE CASSIDY
Drywall Nailing 5/13/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/15/2020 Partial Approval EUGENE CASSIDY
Final 5/15/2020 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 5/15/2020 Approved EUGENE CASSIDY
Green Building Final 5/15/2020 Approved EUGENE CASSIDY
HVAC-Rough 5/15/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 5/15/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/15/2020 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 5/15/2020 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 6/25/2020 Approved EUGENE CASSIDY
Final 6/25/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 6/25/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/25/2020 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 6/25/2020 Approved EUGENE CASSIDY
Final 6/30/2020 Corrections Issued EUGENE CASSIDY
Special/Order Compliance 6/30/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 7/7/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Final 7/7/2020 Corrections Issued ENRIQUE MIRELES
Service/Power Release 7/7/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Final 7/13/2020 Approved JOSEPH MCGARRY
Final 7/13/2020 Corrections Issued JOSEPH MCGARRY
HVAC-Final 7/13/2020 Approved JOSEPH MCGARRY
PLUMBING-Final 7/13/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Final 7/29/2020 Not Ready for Inspection FREDDIE RIVERA
Final 7/29/2020 Not Ready for Inspection FREDDIE RIVERA
Final 8/12/2020 Corrections Issued COREY HUPP
Final 8/14/2020 Conditional Approval SABAS ALONSO
Grounding or Bonding 8/14/2020 Approved SABAS ALONSO
Service/Power Release 8/14/2020 Approved SABAS ALONSO
Final 8/18/2020 OK to Issue CofO COREY HUPP