848-848 1/2 W 68TH ST 90044
Certificate Information: 848-848 1/2 W 68TH ST 90044
- Application / Permit
- 19014-70000-04919
- Plan Check / Job No.
- B19SL01219
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ADDITION AND CONVERSION OF (E) SINGLE FAMILY DWELLING AT REAR OF LOT INTO A DUPLEX
- Permit Issued
- Issued on 1/29/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | ARMEN JIVALAGIAN |
| Corrections Issued | 9/25/2019 | ARMEN JIVALAGIAN |
| Quality Review Completed | 10/2/2019 | TIEN JEN WANG |
| Building Plans Picked Up | 10/11/2019 | APPLICANT |
| Applicant returned to address corrections | 1/3/2020 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/9/2020 | ARMEN JIVALAGIAN |
| Plan Check Approved | 1/24/2020 | ARMEN JIVALAGIAN |
| No Progress | 1/24/2020 | ARMEN JIVALAGIAN |
| Plan Check Approved | 1/24/2020 | ARMEN JIVALAGIAN |
| Issued | 1/29/2020 | LADBS |
| CofO in Progress | 8/18/2020 | COREY HUPP |
| CofO in Progress | 8/18/2020 | COREY HUPP |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
| CofO Issued | 9/3/2020 | DEROLD HAUFF |
| Permit Finaled | 9/3/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/17/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2019 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 12/17/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 12/17/2019 | EMIL KYUPELYAN |
| ZI | Cleared | 12/17/2019 | JASON CHAN |
| Green Code | Cleared | 12/27/2019 | SARAH ABOULHOSN |
Contact Information
| Contractor | Largo Construction Inc; Lic. No.: 1011935-B | 5864 EAST RANCHO DRIVE FRESNO, CA 93727 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/18/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 2/18/2020 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 2/18/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 4/22/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2020 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/30/2020 | Partial Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 4/30/2020 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 4/30/2020 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 5/6/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/6/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/8/2020 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 5/8/2020 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 5/8/2020 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 5/8/2020 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 5/13/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/15/2020 | Partial Approval | EUGENE CASSIDY |
| Final | 5/15/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 5/15/2020 | Approved | EUGENE CASSIDY |
| Green Building Final | 5/15/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/15/2020 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 5/15/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/15/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 5/15/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/25/2020 | Approved | EUGENE CASSIDY |
| Final | 6/25/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 6/25/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/25/2020 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 6/25/2020 | Approved | EUGENE CASSIDY |
| Final | 6/30/2020 | Corrections Issued | EUGENE CASSIDY |
| Special/Order Compliance | 6/30/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 7/7/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 7/7/2020 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 7/7/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/13/2020 | Approved | JOSEPH MCGARRY |
| Final | 7/13/2020 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Final | 7/13/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 7/13/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 7/29/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 7/29/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 8/12/2020 | Corrections Issued | COREY HUPP |
| Final | 8/14/2020 | Conditional Approval | SABAS ALONSO |
| Grounding or Bonding | 8/14/2020 | Approved | SABAS ALONSO |
| Service/Power Release | 8/14/2020 | Approved | SABAS ALONSO |
| Final | 8/18/2020 | OK to Issue CofO | COREY HUPP |