113 E 76TH PL 90003
Certificate Information: 113 E 76TH PL 90003
- Application / Permit
- 19014-70000-04879
- Plan Check / Job No.
- B19SL01215
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO (E) SINGLE FAMILY DWELLING TO EXPLAND ONE BEDROOM, ONE CLOSET AND BATHROOM
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 1/24/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 9/23/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 10/1/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 10/8/2019 | APPLICANT |
| Applicant returned to address corrections | 11/22/2019 | SERGIO GUTIERREZ |
| Plan Check Approved | 12/20/2019 | SERGIO GUTIERREZ |
| Issued | 1/24/2020 | LADBS |
| Green Plans Picked Up | 5/5/2020 | APPLICANT |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 10/15/2019 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2019 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 10/15/2019 | ELAINE LEI |
| Sewer availability | Cleared | 10/15/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 11/8/2019 | JEREMY CARTER |
| Green Code | Cleared | 12/10/2019 | VIVIAN LAO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/1/2020 | Corrections Issued | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 7/16/2020 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 7/16/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/1/2020 | Approved | FREDDIE RIVERA |