1847 W 88TH PL 90047

Certificate Information: 1847 W 88TH PL 90047

Application / Permit
19014-70000-04655
Plan Check / Job No.
B19SL01156
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 2 STORY ADU PER AB 494 AND SB 229
Permit Issued
Issued on 8/16/2020
Issuing Office
Current Status
CofO Issued on 5/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 LAWRENCE QUIRANTE
Corrections Issued 9/11/2019 LAWRENCE QUIRANTE
Quality Review Completed 9/11/2019 GARO TELMI
Building Plans Picked Up 9/27/2019 APPLICANT
Applicant returned to address corrections 12/16/2019 LAWRENCE QUIRANTE
Applicant returned to address corrections 4/14/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 7/2/2020 APPLICANT
Applicant returned to address corrections 7/8/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 7/27/2020 LAWRENCE QUIRANTE
Plan Check Approved 8/14/2020 LAWRENCE QUIRANTE
Issued 8/16/2020 APPLICANT
CofO in Progress 5/6/2025 LUIS CASTRO
Permit Finaled 5/8/2025 DEROLD HAUFF
CofO Issued 5/8/2025 DEROLD HAUFF
Permit Finaled 5/8/2025 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 4/14/2020 DANIEL CORONADO
Community Plan Implem. Overlay Cleared 4/14/2020 DANIEL CORONADO
Address approval Cleared 4/20/2020 EMIL KYUPELYAN
Community Plan Implem. Overlay Cleared 4/22/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 4/22/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 4/22/2020 EMIL KYUPELYAN
Sewer availability Cleared 4/22/2020 EMIL KYUPELYAN
Green Code Cleared 7/1/2020 LAWRENCE QUIRANTE

Contact Information

Contractor Owner-Builder       ,
Engineer Dia,, Gil Aroja; Lic. No.: C26172 532 E 222ND STREET      CARSON, CA 90745

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/9/2021 Conditional Approval FREDDIE RIVERA
Pre-Inspection 3/9/2021 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 3/24/2021 Partial Approval FREDDIE RIVERA
Pre-Inspection 3/24/2021 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 4/7/2021 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 4/23/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 5/4/2021 Not Ready for Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/28/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 4/18/2023 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 4/18/2023 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 4/18/2023 Approved ENRIQUE MIRELES
HVAC-Rough 4/18/2023 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 4/18/2023 Not Ready for Inspection ENRIQUE MIRELES
Verify Sprinkler Sign Off 4/18/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 4/26/2023 Approved ENRIQUE MIRELES
Gas Test 4/26/2023 Approved ENRIQUE MIRELES
HVAC-Rough 4/26/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/26/2023 Approved ENRIQUE MIRELES
Wood Frame 4/26/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 9/25/2023 Corrections Issued ENRIQUE MIRELES
Insulation 10/6/2023 Approved ENRIQUE MIRELES
Drywall Nailing 10/20/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 10/20/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/9/2023 Approved ENRIQUE MIRELES
Pre-Inspection 5/1/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 7/16/2024 Approved JOSE MACIAS
ELECTRICAL-Final 7/16/2024 Corrections Issued JOSE MACIAS
Final 7/16/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 7/16/2024 Approved JOSE MACIAS
Green Building Final 7/16/2024 Approved JOSE MACIAS
HVAC-Final 7/16/2024 Corrections Issued JOSE MACIAS
PLUMBING-Final 7/16/2024 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 7/16/2024 SGSOV Approved JOSE MACIAS
Service/Power Release 7/16/2024 Not Ready for Inspection JOSE MACIAS
Smoke Detectors 7/16/2024 Approved JOSE MACIAS
ELECTRICAL-Final 9/24/2024 Approved AMIR NAZARIAN
Final 9/24/2024 Corrections Issued AMIR NAZARIAN
HVAC-Final 9/24/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Final 9/24/2024 Approved AMIR NAZARIAN
Service/Power Release 9/24/2024 Not Ready for Inspection AMIR NAZARIAN
Final 2/14/2025 Corrections Issued JOSE MACIAS
Final 5/5/2025 OK to Issue CofO LUIS CASTRO
HVAC-Final 5/5/2025 Approved LUIS CASTRO
Service/Power Release 5/5/2025 Approved LUIS CASTRO