2151 W 81ST ST 90047
Certificate Information: 2151 W 81ST ST 90047
- Application / Permit
- 19014-70000-04149
- Plan Check / Job No.
- B19SL01011
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 10/14/2020
- Issuing Office
- Current Status
- CofO Issued on 8/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2019 | RICARDO RAMIREZ |
| Corrections Issued | 8/6/2019 | RICARDO RAMIREZ |
| Quality Review Completed | 8/9/2019 | TEODORO DIAZ RODRIGUEZ |
| Green Plans Picked Up | 9/13/2019 | APPLICANT |
| Applicant returned to address corrections | 11/19/2019 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 8/11/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 8/26/2020 | RICARDO RAMIREZ |
| Building Plans Picked Up | 10/9/2020 | APPLICANT |
| Issued | 10/14/2020 | APPLICANT |
| CofO in Progress | 7/1/2021 | ANDEY CHAPARRO |
| Permit Finaled | 8/9/2021 | BRUCE TODD |
| CofO Issued | 8/9/2021 | BRUCE TODD |
| Permit Finaled | 8/9/2021 | BRUCE TODD |
Permit Application Clearance Information
| Green Code | Cleared | 11/18/2019 | VIVIAN LAO |
| Hydrant and Access approval | Cleared | 11/26/2019 | JEREMY CARTER |
| Construction within easement | Cleared | 1/11/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 7/13/2020 | MITESH PATEL |
| ZI | Cleared | 8/19/2020 | RUBEN VASQUEZ |
| Address approval | Cleared | 8/21/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2020 | ELAINE LEI |
| Sewer availability | Cleared | 8/21/2020 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 8/25/2020 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Brunmier,, David Wayne; Lic. No.: C80545 | 18567 VALLEY BLVD. BLOOMINGTON, CA 92316 |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/30/2020 | Not Ready for Inspection | KIM BEAUCHAMP |
| PLUMBING-Rough | 11/24/2020 | Not Ready for Inspection | KIM DOEPPING |
| Underground Mechanical | 12/1/2020 | Partial Approval | KIM DOEPPING |
| Footing/Foundation/Slab | 12/7/2020 | Approved | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 12/17/2020 | Not Ready for Inspection | KIM DOEPPING |
| BUILDING-Rough-Frame | 12/23/2020 | Not Ready for Inspection | ANDEY CHAPARRO |
| Green Building Rough | 12/23/2020 | Not Ready for Inspection | ANDEY CHAPARRO |
| Underground Mechanical | 1/7/2021 | Partial Approval | ANDEY CHAPARRO |
| BUILDING-Rough-Frame | 1/12/2021 | Not Ready for Inspection | ANDEY CHAPARRO |
| Green Building Rough | 1/12/2021 | Not Ready for Inspection | ANDEY CHAPARRO |
| BUILDING-Rough-Frame | 2/3/2021 | Not Ready for Inspection | ANDEY CHAPARRO |
| ELECTRICAL-Rough | 2/3/2021 | Corrections Issued | ANDEY CHAPARRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2021 | Approved | ANDEY CHAPARRO |
| Green Building Rough | 2/3/2021 | Corrections Issued | ANDEY CHAPARRO |
| HVAC-Rough | 2/3/2021 | Corrections Issued | ANDEY CHAPARRO |
| PLUMBING-Rough | 2/3/2021 | Corrections Issued | ANDEY CHAPARRO |
| Underground Mechanical | 2/3/2021 | Approved | ANDEY CHAPARRO |
| BUILDING-Rough-Frame | 2/18/2021 | Approved | ANDEY CHAPARRO |
| ELECTRICAL-Rough | 2/18/2021 | Approved | ANDEY CHAPARRO |
| Green Building Rough | 2/18/2021 | Approved | ANDEY CHAPARRO |
| HVAC-Rough | 2/18/2021 | Approved | ANDEY CHAPARRO |
| PLUMBING-Rough | 2/18/2021 | Approved | ANDEY CHAPARRO |
| Insulation | 3/2/2021 | Approved | ANDEY CHAPARRO |
| Interior/Exterior Lathing | 3/2/2021 | Partial Approval | ANDEY CHAPARRO |
| Drywall Nailing | 3/16/2021 | Approved | ANDEY CHAPARRO |
| Interior/Exterior Lathing | 3/16/2021 | Approved | ANDEY CHAPARRO |
| Final | 5/11/2021 | Corrections Issued | ANDEY CHAPARRO |
| Green Building Final | 5/11/2021 | Not Ready for Inspection | ANDEY CHAPARRO |
| SGSOV-Seismic Gas S/O Valve | 5/11/2021 | SGSOV Not Ready | ANDEY CHAPARRO |
| Smoke Detectors | 5/11/2021 | Approved | ANDEY CHAPARRO |
| Pre-Inspection | 6/2/2021 | Not Ready for Inspection | ANDEY CHAPARRO |
| Pre-Inspection | 6/11/2021 | Approved | ANDEY CHAPARRO |
| Final | 6/18/2021 | Conditional Approval | KIM DOEPPING |
| Green Building Final | 6/18/2021 | Approved | KIM DOEPPING |
| SGSOV-Seismic Gas S/O Valve | 6/18/2021 | SGSOV Approved | KIM DOEPPING |
| ELECTRICAL-Final | 7/1/2021 | Approved | ANDEY CHAPARRO |
| Final | 7/1/2021 | OK to Issue CofO | ANDEY CHAPARRO |
| HVAC-Final | 7/1/2021 | Approved | ANDEY CHAPARRO |
| PLUMBING-Final | 7/1/2021 | Approved | ANDEY CHAPARRO |
| Service/Power Release | 7/1/2021 | Approved | ANDEY CHAPARRO |