2151 W 81ST ST 90047

Certificate Information: 2151 W 81ST ST 90047

Application / Permit
19014-70000-04149
Plan Check / Job No.
B19SL01011
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 10/14/2020
Issuing Office
Current Status
CofO Issued on 8/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2019 APPLICANT
Assigned to Plan Check Engineer 8/2/2019 RICARDO RAMIREZ
Corrections Issued 8/6/2019 RICARDO RAMIREZ
Quality Review Completed 8/9/2019 TEODORO DIAZ RODRIGUEZ
Green Plans Picked Up 9/13/2019 APPLICANT
Applicant returned to address corrections 11/19/2019 RICARDO RAMIREZ
Applicant returned to address corrections 8/11/2020 RICARDO RAMIREZ
Plan Check Approved 8/26/2020 RICARDO RAMIREZ
Building Plans Picked Up 10/9/2020 APPLICANT
Issued 10/14/2020 APPLICANT
CofO in Progress 7/1/2021 ANDEY CHAPARRO
Permit Finaled 8/9/2021 BRUCE TODD
CofO Issued 8/9/2021 BRUCE TODD
Permit Finaled 8/9/2021 BRUCE TODD

Permit Application Clearance Information

Green Code Cleared 11/18/2019 VIVIAN LAO
Hydrant and Access approval Cleared 11/26/2019 JEREMY CARTER
Construction within easement Cleared 1/11/2020 RIDWAN HARDY
Low Impact Development Cleared 7/13/2020 MITESH PATEL
ZI Cleared 8/19/2020 RUBEN VASQUEZ
Address approval Cleared 8/21/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 8/21/2020 ELAINE LEI
Sewer availability Cleared 8/21/2020 ELAINE LEI
Roof/Waste drainage to street Cleared 8/25/2020 ELAINE LEI

Contact Information

Contractor Owner-Builder       ,
Engineer Brunmier,, David Wayne; Lic. No.: C80545 18567 VALLEY BLVD.      BLOOMINGTON, CA 92316

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/30/2020 Not Ready for Inspection KIM BEAUCHAMP
PLUMBING-Rough 11/24/2020 Not Ready for Inspection KIM DOEPPING
Underground Mechanical 12/1/2020 Partial Approval KIM DOEPPING
Footing/Foundation/Slab 12/7/2020 Approved DANIEL GONZALEZ
BUILDING-Rough-Frame 12/17/2020 Not Ready for Inspection KIM DOEPPING
BUILDING-Rough-Frame 12/23/2020 Not Ready for Inspection ANDEY CHAPARRO
Green Building Rough 12/23/2020 Not Ready for Inspection ANDEY CHAPARRO
Underground Mechanical 1/7/2021 Partial Approval ANDEY CHAPARRO
BUILDING-Rough-Frame 1/12/2021 Not Ready for Inspection ANDEY CHAPARRO
Green Building Rough 1/12/2021 Not Ready for Inspection ANDEY CHAPARRO
BUILDING-Rough-Frame 2/3/2021 Not Ready for Inspection ANDEY CHAPARRO
ELECTRICAL-Rough 2/3/2021 Corrections Issued ANDEY CHAPARRO
Floor/Roof Diaphrgm/Shear Wall 2/3/2021 Approved ANDEY CHAPARRO
Green Building Rough 2/3/2021 Corrections Issued ANDEY CHAPARRO
HVAC-Rough 2/3/2021 Corrections Issued ANDEY CHAPARRO
PLUMBING-Rough 2/3/2021 Corrections Issued ANDEY CHAPARRO
Underground Mechanical 2/3/2021 Approved ANDEY CHAPARRO
BUILDING-Rough-Frame 2/18/2021 Approved ANDEY CHAPARRO
ELECTRICAL-Rough 2/18/2021 Approved ANDEY CHAPARRO
Green Building Rough 2/18/2021 Approved ANDEY CHAPARRO
HVAC-Rough 2/18/2021 Approved ANDEY CHAPARRO
PLUMBING-Rough 2/18/2021 Approved ANDEY CHAPARRO
Insulation 3/2/2021 Approved ANDEY CHAPARRO
Interior/Exterior Lathing 3/2/2021 Partial Approval ANDEY CHAPARRO
Drywall Nailing 3/16/2021 Approved ANDEY CHAPARRO
Interior/Exterior Lathing 3/16/2021 Approved ANDEY CHAPARRO
Final 5/11/2021 Corrections Issued ANDEY CHAPARRO
Green Building Final 5/11/2021 Not Ready for Inspection ANDEY CHAPARRO
SGSOV-Seismic Gas S/O Valve 5/11/2021 SGSOV Not Ready ANDEY CHAPARRO
Smoke Detectors 5/11/2021 Approved ANDEY CHAPARRO
Pre-Inspection 6/2/2021 Not Ready for Inspection ANDEY CHAPARRO
Pre-Inspection 6/11/2021 Approved ANDEY CHAPARRO
Final 6/18/2021 Conditional Approval KIM DOEPPING
Green Building Final 6/18/2021 Approved KIM DOEPPING
SGSOV-Seismic Gas S/O Valve 6/18/2021 SGSOV Approved KIM DOEPPING
ELECTRICAL-Final 7/1/2021 Approved ANDEY CHAPARRO
Final 7/1/2021 OK to Issue CofO ANDEY CHAPARRO
HVAC-Final 7/1/2021 Approved ANDEY CHAPARRO
PLUMBING-Final 7/1/2021 Approved ANDEY CHAPARRO
Service/Power Release 7/1/2021 Approved ANDEY CHAPARRO