2006 W 73RD ST 90047
Certificate Information: 2006 W 73RD ST 90047
- Application / Permit
- 19014-70000-03843
- Plan Check / Job No.
- B19SL00931
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to (e) garage to convert into ADU per AB 494 and SB 229.
- Permit Issued
- Issued on 1/7/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2019 | RICARDO RAMIREZ |
| Corrections Issued | 11/25/2019 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 11/25/2019 | PRANITA SHAH |
| Plan Check Approved | 11/27/2019 | LUKE GONZALES |
| Issued | 1/7/2020 | LADBS |
| CofO in Progress | 1/20/2021 | FREDDIE RIVERA |
| Permit Finaled | 2/16/2023 | DANIEL ORRANTE |
| CofO Issued | 2/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2019 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 8/21/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 8/21/2019 | ERIK BEASLEY |
| ZI | Cleared | 8/21/2019 | SARAHI ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2019 | ROBYN STEELE |
| Construction near power lines | Cleared | 11/3/2019 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 11/27/2019 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/13/2020 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/27/2020 | Partial Approval | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 2/12/2020 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 2/18/2020 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 5/5/2020 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 8/5/2020 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/17/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 8/17/2020 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/2/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 9/2/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 9/2/2020 | Approved | FREDDIE RIVERA |
| Insulation | 9/21/2020 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/21/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 10/7/2020 | Approved | FREDDIE RIVERA |
| Final | 1/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 1/4/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 1/4/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 1/4/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 1/14/2021 | Corrections Issued | FREDDIE RIVERA |
| Smoke Detectors | 1/14/2021 | Approved | FREDDIE RIVERA |
| Final | 1/19/2021 | OK to Issue CofO | FREDDIE RIVERA |