2222 N GLOVER PL 90031
Certificate Information: 2222 N GLOVER PL 90031
- Application / Permit
- 19014-70000-03139
- Plan Check / Job No.
- B19SL00759
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to rear of (e) one story single family dwelling.
- Permit Issued
- Issued on 7/3/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2019 | RICARDO RAMIREZ |
| Corrections Issued | 6/11/2019 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 6/17/2019 | RICARDO RAMIREZ |
| Plan Check Approved | 6/19/2019 | TEODORO DIAZ RODRIGUEZ |
| Issued | 7/3/2019 | LADBS |
| CofO in Progress | 12/16/2021 | SCOTT FINNILA |
| Permit Finaled | 12/18/2021 | DEROLD HAUFF |
| CofO Issued | 12/18/2021 | DEROLD HAUFF |
| Permit Finaled | 12/18/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2019 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 6/13/2019 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/13/2019 | ADRIAN SANCHEZ |
Contact Information
| Contractor | A & S Constructors Inc; Lic. No.: 921776-B | 937 MIRA VALLE ST MONTEREY PARK, CA 91754 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/24/2019 | Approved | DAVID CHAN |
| Deputy Drilled-In Anchors | 7/25/2019 | Conditional Approval | DAVID CHAN |
| PLUMBING-Rough | 8/9/2019 | Approved | ELMER BLAND |
| ELECTRICAL-Rough | 2/7/2020 | Corrections Issued | AJA COLLAY |
| Insulation | 2/7/2020 | Corrections Issued | AJA COLLAY |
| Interior/Exterior Lathing | 2/7/2020 | Corrections Issued | AJA COLLAY |
| ELECTRICAL-Rough | 2/12/2020 | Not Ready for Inspection | HORACE FULTZ |
| Insulation | 2/12/2020 | Not Ready for Inspection | HORACE FULTZ |
| Interior/Exterior Lathing | 2/12/2020 | Not Ready for Inspection | HORACE FULTZ |
| Wood Frame | 2/12/2020 | Not Ready for Inspection | HORACE FULTZ |
| BUILDING-Rough-Frame | 3/6/2020 | Corrections Issued | AJA COLLAY |
| PLUMBING-Rough | 3/16/2020 | Corrections Issued | AJA COLLAY |
| PLUMBING-Rough | 4/2/2020 | Approved | GORDON ZUBER |
| BUILDING-Rough-Frame | 12/1/2021 | Approved | SCOTT FINNILA |
| Drywall Nailing | 12/1/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 12/1/2021 | Approved | SCOTT FINNILA |
| Final | 12/1/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 12/1/2021 | Approved | SCOTT FINNILA |
| Green Building Rough | 12/1/2021 | Approved | SCOTT FINNILA |
| HVAC-Final | 12/1/2021 | Approved | SCOTT FINNILA |
| MERV13>=Final | 12/1/2021 | Approved | SCOTT FINNILA |
| MERV13>=Rough | 12/1/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 12/1/2021 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/1/2021 | SGSOV Approved | SCOTT FINNILA |
| Service/Power Release | 12/1/2021 | Corrections Issued | SCOTT FINNILA |
| Smoke Detectors | 12/1/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 12/15/2021 | Approved | SCOTT FINNILA |
| Final | 12/15/2021 | OK to Issue CofO | SCOTT FINNILA |
| HVAC-Final | 12/15/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 12/15/2021 | Approved | SCOTT FINNILA |
| Service/Power Release | 12/15/2021 | Approved | SCOTT FINNILA |