3401 S COCHRAN AVE 90016

Certificate Information: 3401 S COCHRAN AVE 90016

Application / Permit
19014-70000-02388
Plan Check / Job No.
B19SL00564
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE 15'-7" x 16'-7" (E)PATIO COVER AT REAR OF (E)SINGLE FAMILY DWELLING AND MAKE IT A NEW MASTER BATHROOM AND CLOSET.
Permit Issued
Issued on 7/15/2020
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2019 APPLICANT
Assigned to Plan Check Engineer 6/7/2019 RAHEL BEYENE
Corrections Issued 6/10/2019 SARKIS HARABEDIAN
Green Plans Picked Up 6/19/2019 APPLICANT
Quality Review Completed 6/24/2019 ABDUL CHEGENI
Building Plans Picked Up 8/5/2019 APPLICANT
Applicant returned to address corrections 10/4/2019 RAHEL BEYENE
Applicant returned to address corrections 11/5/2019 RAHEL BEYENE
Plan Check Approved 11/14/2019 RAHEL BEYENE
Issued 7/15/2020 APPLICANT
CofO in Progress 3/9/2021 SCOTT FINNILA
Permit Finaled 3/4/2023 DANIEL ORRANTE
CofO Issued 3/4/2023 DANIEL ORRANTE
Permit Finaled 3/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Metro Rail approval Cleared 10/25/2019 SARKIS HARABEDIAN
Eng Process Fee Ord 176,300 Cleared 11/5/2019 THOMAS LANG
Roof/Waste drainage to street Cleared 11/5/2019 THOMAS LANG
Sewer availability Cleared 11/5/2019 THOMAS LANG
Green Code Cleared 11/14/2019 SARAH ABOULHOSN

Contact Information

Contractor Owner-Builder       ,
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/31/2020 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 9/10/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 9/25/2020 Partial Approval DAVID CHAN
Wood Frame 9/25/2020 No Access for Inspection DAVID CHAN
BUILDING-Rough-Frame 10/26/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 10/26/2020 Corrections Issued DAVID CHAN
PLUMBING-Rough 10/26/2020 Not Ready for Inspection DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Approved DAVID CHAN
ELECTRICAL-Rough 11/2/2020 Approved DAVID CHAN
Insulation 11/2/2020 Conditional Approval DAVID CHAN
PLUMBING-Rough 11/2/2020 Approved DAVID CHAN
Drywall Nailing 11/9/2020 Approved DAVID CHAN
Interior/Exterior Lathing 11/19/2020 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 2/18/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 2/18/2021 Corrections Issued KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 2/18/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 2/18/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/1/2021 Approved SCOTT FINNILA
Final 3/1/2021 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 3/1/2021 SGSOV Approved SCOTT FINNILA
Smoke Detectors 3/1/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 3/8/2021 Approved SCOTT FINNILA
Final 3/8/2021 OK to Issue CofO SCOTT FINNILA
HVAC-Final 3/8/2021 Approved SCOTT FINNILA
PLUMBING-Final 3/8/2021 Approved SCOTT FINNILA
Smoke Detectors 3/8/2021 Approved SCOTT FINNILA