3401 S COCHRAN AVE 90016
Certificate Information: 3401 S COCHRAN AVE 90016
- Application / Permit
- 19014-70000-02388
- Plan Check / Job No.
- B19SL00564
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE 15'-7" x 16'-7" (E)PATIO COVER AT REAR OF (E)SINGLE FAMILY DWELLING AND MAKE IT A NEW MASTER BATHROOM AND CLOSET.
- Permit Issued
- Issued on 7/15/2020
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2019 | RAHEL BEYENE |
| Corrections Issued | 6/10/2019 | SARKIS HARABEDIAN |
| Green Plans Picked Up | 6/19/2019 | APPLICANT |
| Quality Review Completed | 6/24/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 8/5/2019 | APPLICANT |
| Applicant returned to address corrections | 10/4/2019 | RAHEL BEYENE |
| Applicant returned to address corrections | 11/5/2019 | RAHEL BEYENE |
| Plan Check Approved | 11/14/2019 | RAHEL BEYENE |
| Issued | 7/15/2020 | APPLICANT |
| CofO in Progress | 3/9/2021 | SCOTT FINNILA |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 10/25/2019 | SARKIS HARABEDIAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2019 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 11/5/2019 | THOMAS LANG |
| Sewer availability | Cleared | 11/5/2019 | THOMAS LANG |
| Green Code | Cleared | 11/14/2019 | SARAH ABOULHOSN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/31/2020 | Corrections Issued | DAVID CHAN |
| Footing/Foundation/Slab | 9/10/2020 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 9/25/2020 | Partial Approval | DAVID CHAN |
| Wood Frame | 9/25/2020 | No Access for Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 10/26/2020 | Corrections Issued | DAVID CHAN |
| ELECTRICAL-Rough | 10/26/2020 | Corrections Issued | DAVID CHAN |
| PLUMBING-Rough | 10/26/2020 | Not Ready for Inspection | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Rough | 11/2/2020 | Approved | DAVID CHAN |
| Insulation | 11/2/2020 | Conditional Approval | DAVID CHAN |
| PLUMBING-Rough | 11/2/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 11/9/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 11/19/2020 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 2/18/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 2/18/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 2/18/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 2/18/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 3/1/2021 | Approved | SCOTT FINNILA |
| Final | 3/1/2021 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 3/1/2021 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 3/1/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 3/8/2021 | Approved | SCOTT FINNILA |
| Final | 3/8/2021 | OK to Issue CofO | SCOTT FINNILA |
| HVAC-Final | 3/8/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 3/8/2021 | Approved | SCOTT FINNILA |