5837 N RIVERTON AVE 91601

Certificate Information: 5837 N RIVERTON AVE 91601

Application / Permit
19014-70000-01921
Plan Check / Job No.
B19SL00465
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 20' X 20' IRREGULAR SHAPED PORTION OF GARAGE; ADD 20' X 32' (2) STORY TO AND CONVERT 15' X 17' GARAGE TO ACCESSORY DWELLING UNIT PER AB494 AND SB229
Permit Issued
Issued on 2/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2019 APPLICANT
Assigned to Plan Check Engineer 5/23/2019 SELLA BENYAMIN
Corrections Issued 5/29/2019 SELLA BENYAMIN
Quality Review Completed 5/30/2019 FELIX FIGUEROA
Green Plans Picked Up 6/6/2019 APPLICANT
Building Plans Picked Up 7/3/2019 APPLICANT
Plan Check Approved 8/15/2019 SELLA BENYAMIN
Issued 2/11/2020 LADBS
CofO in Progress 8/2/2022 CALEB MEISTER
CofO Issued 8/24/2022 DANIEL ORRANTE
Permit Finaled 8/24/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/18/2019 JEANETTE VONG
Green Code Cleared 6/18/2019 SARAH ABOULHOSN
Eng Process Fee Ord 176,300 Cleared 7/12/2019 ELAINE LEI
Hydrant and Access approval Cleared 7/12/2019 JOHN CONNEALLY
Sewer availability Cleared 7/12/2019 ELAINE LEI
Low Impact Development Cleared 7/24/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/24/2019 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/26/2020 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 3/26/2020 Not Ready for Inspection BRENDAN LOONEY
Pre-Inspection 3/26/2020 Not Ready for Inspection BRENDAN LOONEY
Interior/Exterior Lathing 3/5/2021 Approved DANIEL DREW
ELECTRICAL-Rough 3/9/2021 Partial Approval DANIEL DREW
PLUMBING-Rough 3/9/2021 Corrections Issued DANIEL DREW
ELECTRICAL-Rough 4/26/2021 No Access for Inspection STEVEN BACK
HVAC-Rough 4/26/2021 No Access for Inspection STEVEN BACK
Insulation 4/26/2021 No Access for Inspection STEVEN BACK
PLUMBING-Rough 4/26/2021 No Access for Inspection STEVEN BACK
Insulation 5/27/2021 Not Ready for Inspection ARAM AVEDISIAN
HVAC-Rough 6/4/2021 No Access for Inspection RICHARD DOCKUS
Insulation 6/4/2021 No Access for Inspection RICHARD DOCKUS
Underground Mechanical 6/4/2021 Partial Approval ARAM AVEDISIAN
HVAC-Rough 6/10/2021 Approved RONALD COWAN
Underground Mechanical 6/10/2021 Partial Approval RONALD COWAN
ELECTRICAL-Rough 6/30/2021 Approved DANIEL DREW
Gas Test 6/30/2021 Approved DANIEL DREW
Insulation 6/30/2021 Approved DANIEL DREW
PLUMBING-Rough 6/30/2021 Approved DANIEL DREW
Service/Power Release 6/30/2021 Not Ready for Inspection DANIEL DREW
Drywall Nailing 8/4/2021 Approved DANIEL DREW
Shower Pan 8/4/2021 Not Ready for Inspection DANIEL DREW
Interior/Exterior Lathing 8/12/2021 Approved DANIEL DREW
Shower Pan 8/12/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 2/9/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/9/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 2/9/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 2/9/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Final 2/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 2/9/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 2/9/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 2/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 5/31/2022 Corrections Issued MATT KELLERMAN
Green Building Final 5/31/2022 Approved MATT KELLERMAN
Service/Power Release 5/31/2022 Corrections Issued MATT KELLERMAN
Smoke Detectors 5/31/2022 Approved MATT KELLERMAN
Final 7/13/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Final 8/1/2022 Approved CALEB MEISTER
Final 8/1/2022 OK to Issue CofO CALEB MEISTER
HVAC-Final 8/1/2022 Approved CALEB MEISTER
HVAC-Rough 8/1/2022 Approved CALEB MEISTER
PLUMBING-Final 8/1/2022 Approved CALEB MEISTER
Service/Power Release 8/1/2022 Approved CALEB MEISTER