1026 W 60TH PL 90044
Certificate Information: 1026 W 60TH PL 90044
- Application / Permit
- 19014-70000-01838
- Plan Check / Job No.
- B19SL00439
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION FOR A BATHROOM AT REAR AND. ALL WORK PER WFPP "COMPLY WITH DEPARTMENT ORDER effective date 01/06/2016. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 2/3/2020
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 2/3/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2019 | LUKE GONZALES |
| Corrections Issued | 4/10/2019 | LUKE GONZALES |
| Applicant returned to address corrections | 5/21/2019 | RICARDO RAMIREZ |
| Issued | 2/3/2020 | LADBS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/1/2019 | ZIXUAN CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 6/5/2019 | ELENA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/3/2020 | Corrections Issued | HECTOR RODRIGUEZ |
| Pre-Inspection | 6/3/2020 | Partial Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 8/5/2020 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Deputy Drilled-In Anchors | 8/14/2020 | Approved | MARIO CUEVAS |
| Footing/Foundation/Slab | 8/25/2020 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/17/2021 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 2/4/2022 | Approved | MEL KHACHATOURIAN |
| Rough-Elec/Plmb/HVAC | 2/18/2022 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 4/6/2022 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 6/17/2022 | Approved | MEL KHACHATOURIAN |
| Final | 6/17/2022 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 6/17/2022 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 6/17/2022 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Not Ready | MEL KHACHATOURIAN |
| Smoke Detectors | 6/17/2022 | Corrections Issued | MEL KHACHATOURIAN |
| Final | 12/9/2022 | Conditional Approval | MARIO CUEVAS |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | MARIO CUEVAS |
| Smoke Detectors | 12/9/2022 | Approved | MARIO CUEVAS |