6744 S ARLINGTON AVE 90043
Certificate Information: 6744 S ARLINGTON AVE 90043
- Application / Permit
- 19014-70000-01698
- Plan Check / Job No.
- B19SL00414
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADDITION TO (E) GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 1/25/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2019 | VU NGUYEN |
| Corrections Issued | 5/17/2019 | VU NGUYEN |
| Quality Review Completed | 5/31/2019 | MICHAEL PEREZ |
| Building Plans Picked Up | 8/26/2019 | APPLICANT |
| Green Plans Picked Up | 9/22/2020 | APPLICANT |
| Applicant returned to address corrections | 10/8/2020 | VU NGUYEN |
| Plan Check Approved | 10/29/2020 | VU NGUYEN |
| Issued | 1/25/2021 | APPLICANT |
| CofO in Progress | 1/29/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 2/5/2024 | DEROLD HAUFF |
| CofO Issued | 2/5/2024 | DEROLD HAUFF |
| Permit Finaled | 2/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/27/2019 | THOMAS LANG |
| Sewer availability | Cleared | 11/27/2019 | THOMAS LANG |
| ZA Case | Cleared | 11/27/2019 | SARAHI ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2020 | PAMELA TENEZA |
| Green Code | Cleared | 9/16/2020 | VU NGUYEN |
| Roof/Waste drainage to street | Cleared | 10/22/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-B | 3684 E PERCY ST LOS ANGELES, CA 90023 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/27/2021 | Corrections Issued | FREDDIE RIVERA |
| Underground Mechanical | 4/27/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/12/2021 | Approved | FREDDIE RIVERA |
| Wood Frame | 5/10/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/9/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 6/9/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 6/9/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 8/26/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/26/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/13/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/22/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/2/2023 | No Access for Inspection | LILIANA PORTILLO |
| Pre-Inspection | 4/28/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/8/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 6/21/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/11/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | DAVID FEILER |
| Final | 9/12/2023 | Not Ready for Inspection | DAVID FEILER |
| Green Building Final | 9/12/2023 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 9/12/2023 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/12/2023 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 9/12/2023 | Not Ready for Inspection | DAVID FEILER |
| Final | 12/8/2023 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/8/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 12/8/2023 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/8/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/24/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 1/29/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |