11741-11743 N FENTON AVE 91342

Certificate Information: 11741-11743 N FENTON AVE 91342

Application / Permit
19014-70000-01469
Plan Check / Job No.
B19SL00365
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REAR ADDITION TO (E) SINGLE FAMILY DWELLING TO CREATE BEDROOM, BATHROOM AND COVER PATIO PER WFPP (P/BC-2017-004).
Permit Issued
Issued on 8/6/2019
Issuing Office
Metro
Current Status
CofO Issued on 3/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2019 APPLICANT
Assigned to Plan Check Engineer 3/22/2019 JOSHUA DIAZ
Corrections Issued 3/22/2019 JOSHUA DIAZ
Plan Check Approved 6/7/2019 AUNG SOE
Issued 8/6/2019 LADBS
CofO in Progress 5/28/2021 MICHEL ABAJAN
Permit Finaled 3/10/2022 RONALD MYRICK
CofO Issued 3/10/2022 RONALD MYRICK
Permit Finaled 3/10/2022 RONALD MYRICK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/3/2019 PATRICK MISCHLICH
Sewer availability Cleared 5/20/2019 CELINA MORENO
Low Impact Development Cleared 6/6/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/6/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 6/7/2019 ROBYN STEELE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/16/2020 No Access for Inspection MICHEL ABAJAN
METHANE-Barrier 1/23/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 1/23/2020 Approved MICHEL ABAJAN
Pre-Inspection 1/23/2020 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/12/2020 Partial Approval MICHEL ABAJAN
Wood Frame 2/12/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/16/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/16/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 3/16/2020 Approved MICHEL ABAJAN
Insulation 3/24/2020 Approved MICHEL ABAJAN
Drywall Nailing 4/7/2020 Approved MICHEL ABAJAN
Drywall Nailing 4/8/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/30/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 11/30/2020 Approved MICHEL ABAJAN
Final 11/30/2020 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 11/30/2020 Approved MICHEL ABAJAN
Green Building Final 11/30/2020 Approved MICHEL ABAJAN
Green Building Rough 11/30/2020 Approved MICHEL ABAJAN
HVAC-Final 11/30/2020 Approved MICHEL ABAJAN
METHANE-Final 11/30/2020 Approved MICHEL ABAJAN
METHANE-Rough 11/30/2020 Approved MICHEL ABAJAN
PLUMBING-Final 11/30/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/30/2020 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 11/30/2020 Approved MICHEL ABAJAN
Final 5/28/2021 OK to Issue CofO MICHEL ABAJAN