731 E 90TH ST 90002
Certificate Information: 731 E 90TH ST 90002
- Application / Permit
- 19014-70000-01409
- Plan Check / Job No.
- B19SL00344
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REAR ADDITION TO (E) SINGLE FAMILY DWELLING TO CREATE NEW FAMILY ROOM, BEDROOM AND BATHROOM.
- Permit Issued
- Issued on 11/14/2019
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 11/14/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2019 | JOSHUA DIAZ |
| Corrections Issued | 3/20/2019 | JOSHUA DIAZ |
| Issued | 11/14/2019 | LADBS |
Permit Application Clearance Information
| Hold | Cleared | 4/3/2019 | MARIA V VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2019 | THOMAS LANG |
| Sewer availability | Cleared | 10/16/2019 | THOMAS LANG |
| Low Impact Development | Cleared | 11/8/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/8/2019 | JAMES MORALEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/16/2020 | Corrections Issued | WILLIAM ROSE |
| Footing/Foundation/Slab | 3/25/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/30/2025 | Partial Inspection | JOHN QUINTANILLA |
| Final | 12/30/2025 | Partial Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 12/30/2025 | Partial Inspection | JOHN QUINTANILLA |
| Green Building Final | 12/30/2025 | Partial Inspection | JOHN QUINTANILLA |
| Green Building Rough | 12/30/2025 | Partial Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Ready | JOHN QUINTANILLA |
| Smoke Detectors | 12/30/2025 | Partial Inspection | JOHN QUINTANILLA |