2734 S RIMPAU BLVD 90016

Certificate Information: 2734 S RIMPAU BLVD 90016

Application / Permit
19014-70000-00136
Plan Check / Job No.
B19SL00035
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 2 CAR GARAGE, REC ROOM AND ADD 90 SQFT TO CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 1/27/2022
Issuing Office
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2019 APPLICANT
Assigned to Plan Check Engineer 2/1/2019 LUKE GONZALES
Corrections Issued 2/5/2019 LUKE GONZALES
Quality Review Completed 2/27/2019 WESLEY FARRELL
Applicant returned to address corrections 3/6/2019 LUKE GONZALES
Green Plans Picked Up 4/9/2019 APPLICANT
Plan Check Approved 6/9/2021 LUKE GONZALES
Building Plans Picked Up 7/15/2021 APPLICANT
Issued 1/27/2022 APPLICANT
CofO in Progress 12/14/2022 CALEB MEISTER
CofO Issued 2/15/2023 DEROLD HAUFF
Permit Finaled 2/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 1/18/2019 NEGAR NEJAD
Address approval Cleared 2/22/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 2/22/2019 ELAINE LEI
Roof/Waste drainage to street Cleared 2/22/2019 ELAINE LEI
Sewer availability Cleared 2/22/2019 ELAINE LEI
Construction near power lines Cleared 8/23/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/27/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 6/13/2022 Approved STUART CHAPMAN
Wood Frame 8/3/2022 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 8/18/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/18/2022 Partial Approval STUART CHAPMAN
HVAC-Rough 8/29/2022 Corrections Issued STUART CHAPMAN
Insulation 8/29/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 9/13/2022 Approved STUART CHAPMAN
Drywall Nailing 9/13/2022 Approved STUART CHAPMAN
Green Building Rough 9/13/2022 Approved STUART CHAPMAN
HVAC-Rough 9/13/2022 Approved STUART CHAPMAN
Insulation 9/13/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 9/13/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 9/13/2022 Approved STUART CHAPMAN
Final 11/7/2022 Corrections Issued STUART CHAPMAN
Green Building Final 11/7/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 11/7/2022 Approved STUART CHAPMAN
Final 11/28/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 12/1/2022 Partial Inspection BRENDAN MORELLI
ELECTRICAL-Final 12/13/2022 Approved CALEB MEISTER
Final 12/13/2022 OK to Issue CofO CALEB MEISTER
HVAC-Final 12/13/2022 Approved CALEB MEISTER
PLUMBING-Final 12/13/2022 Approved CALEB MEISTER