1022 N GULF AVE 90744
Certificate Information: 1022 N GULF AVE 90744
- Application / Permit
- 19014-40002-00962
- Plan Check / Job No.
- B19SP01299
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Supplemental to 19014-20000-00962 to replace lost set of plans and to increase scope of work to be: "One-story, ground floor addition to the rear of (E) garage to create new Accessory Dwelling Unit per SB229 and AB494 with attached garage. All work per WFPP."
- Permit Issued
- Issued on 2/14/2020
- Issuing Office
- San Pedro
- Current Status
- Permit Finaled on 4/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | JASON JANGADA |
| Green Plans Picked Up | 8/29/2019 | APPLICANT |
| Corrections Issued | 9/4/2019 | JASON JANGADA |
| Quality Review Completed | 9/6/2019 | CHRISTOPHER KOMANCHECK |
| Building Plans Picked Up | 1/10/2020 | APPLICANT |
| Applicant returned to address corrections | 1/14/2020 | JASON JANGADA |
| Applicant returned to address corrections | 1/28/2020 | JASON JANGADA |
| Applicant returned to address corrections | 2/4/2020 | JASON JANGADA |
| Applicant returned to address corrections | 2/13/2020 | JASON JANGADA |
| Plan Check Approved | 2/14/2020 | JASON JANGADA |
| Issued | 2/14/2020 | LADBS |
| Permit Finaled | 4/5/2021 | JOHN KLARIN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2019 | PHILLIP WILSON |
| Roof/Waste drainage to street | Cleared | 10/9/2019 | PHILLIP WILSON |
| Sewer availability | Cleared | 10/9/2019 | PHILLIP WILSON |
| Clean Up Green Up | Cleared | 10/10/2019 | ANNA VAN |
| Low Impact Development | Cleared | 10/25/2019 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 11/1/2019 | RICHARD GARCIA |
| Hydrant and Access approval | Cleared | 2/13/2020 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/16/2020 | Not Ready for Inspection | JOHN KLARIN |
| METHANE-Barrier | 3/16/2020 | Corrections Issued | JOHN KLARIN |
| METHANE-Subgrade | 3/16/2020 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 3/19/2020 | Approved | JOHN KLARIN |
| METHANE-Barrier | 3/19/2020 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 3/19/2020 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 4/2/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2020 | Partial Approval | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 5/19/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 5/19/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 5/19/2020 | Approved | JOHN KLARIN |
| METHANE-Rough | 5/19/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 5/19/2020 | Approved | JOHN KLARIN |
| Insulation | 6/4/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 6/4/2020 | Partial Approval | BRIAN CHRISTIAN |
| Drywall Nailing | 6/11/2020 | Corrections Issued | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 6/11/2020 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 6/16/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 7/21/2020 | Approved | JOHN KLARIN |
| Shower Pan | 7/21/2020 | Approved | JOHN KLARIN |
| Final | 8/17/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 8/17/2020 | Corrections Issued | JOHN KLARIN |
| Smoke Detectors | 8/17/2020 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 8/26/2020 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 8/26/2020 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 9/10/2020 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 9/17/2020 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 10/8/2020 | Corrections Issued | JOHN KLARIN |
| Final | 12/21/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 12/21/2020 | Corrections Issued | JOHN KLARIN |
| Smoke Detectors | 12/21/2020 | Not Ready for Inspection | JOHN KLARIN |
| Final | 3/17/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 3/17/2021 | Approved | JOHN KLARIN |
| Smoke Detectors | 3/17/2021 | Approved | JOHN KLARIN |
| PLUMBING-Final | 3/23/2021 | Approved | JOHN KLARIN |
| Final | 4/5/2021 | Permit Finaled | JOHN KLARIN |