4030-4032 W GARDEN AVE 90039

Certificate Information: 4030-4032 W GARDEN AVE 90039

Application / Permit
19014-40000-07141
Plan Check / Job No.
B19SP01944
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Addition to (E) duplex.
Permit Issued
Issued on 5/5/2021
Issuing Office
Current Status
CofO Issued on 7/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 JASON JANGADA
Corrections Issued 2/7/2020 JASON JANGADA
Quality Review Completed 2/14/2020 CHRISTOPHER KOMANCHECK
Green Plans Picked Up 2/14/2020 APPLICANT
Building Plans Picked Up 2/21/2020 APPLICANT
Applicant returned to address corrections 2/10/2021 JASON JANGADA
Applicant returned to address corrections 2/19/2021 JASON JANGADA
Applicant returned to address corrections 3/9/2021 JASON JANGADA
Applicant returned to address corrections 3/19/2021 JASON JANGADA
Plan Check Approved 4/1/2021 JASON JANGADA
Issued 5/5/2021 APPLICANT
CofO in Progress 7/15/2021 HAMIK HARTOUNIAN
Permit Finaled 7/20/2021 DEROLD HAUFF
CofO Issued 7/20/2021 DEROLD HAUFF
Permit Finaled 7/20/2021 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 11/13/2020 MAXFIELD VERMY
ZI Cleared 11/13/2020 MAXFIELD VERMY
Roof/Waste drainage to street Cleared 11/17/2020 JUAN ASHTON
Sewer availability Cleared 11/17/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 11/18/2020 JUAN ASHTON
Hydrant and Access approval Cleared 12/17/2020 MATTHEW CRAIG
Tenant Habitability Plan Cleared 1/21/2021 RICHARD BRINSON
Green Code Cleared 3/9/2021 DONALD CRICHLOW

Contact Information

Contractor Quality Home Remodeling Inc; Lic. No.: 872135-B 245 KANAN RD      OAK PARK, CA 91377
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/13/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/1/2021 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 6/1/2021 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/16/2021 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 6/16/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/24/2021 Approved HAMIK HARTOUNIAN
Insulation 6/24/2021 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Corrections Issued HAMIK HARTOUNIAN
Insulation 6/29/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 7/2/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/12/2021 Approved HAMIK HARTOUNIAN
Final 7/12/2021 OK to Issue CofO HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/12/2021 Approved HAMIK HARTOUNIAN
Green Building Final 7/12/2021 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 7/12/2021 Approved HAMIK HARTOUNIAN