1712 W 257TH ST 90717

Certificate Information: 1712 W 257TH ST 90717

Application / Permit
19014-40000-06942
Plan Check / Job No.
B19SP01921
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER ORDINANCE, SPECIFICALLY 2-STORY A.D.U. ADDITION (1170 SF) TO EXISTING 1-STORY DETACHED GARAGE.
Permit Issued
Issued on 2/5/2021
Issuing Office
Current Status
CofO Issued on 2/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2020 CATHERINE CHEN
Corrections Issued 2/14/2020 CATHERINE CHEN
Quality Review Completed 3/2/2020 MINYE PAK
Building Plans Picked Up 3/4/2020 APPLICANT
Applicant returned to address corrections 6/16/2020 CATHERINE CHEN
Applicant returned to address corrections 6/29/2020 CATHERINE CHEN
Green Plans Picked Up 1/19/2021 APPLICANT
Plan Check Approved 1/29/2021 CATHERINE CHEN
Issued 2/5/2021 APPLICANT
CofO in Progress 12/3/2021 JOHN KLARIN
CofO in Progress 12/8/2021 JOHN KLARIN
CofO in Progress 1/31/2022 EUGENE CASSIDY
No Progress 2/17/2022 ANSON MAGLASANG
CofO in Progress 2/22/2022 ANSON MAGLASANG
Permit Finaled 2/24/2022 DEROLD HAUFF
CofO Issued 2/24/2022 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 3/4/2020 JOE LUCKEY
Address approval Cleared 5/13/2020 CHINH DINH
Address approval Cleared 5/13/2020 CHINH DINH
Green Code Cleared 7/8/2020 RICHARD GARCIA
Low Impact Development Cleared 12/16/2020 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 12/17/2020 CHINH DINH
Roof/Waste drainage to street Cleared 12/17/2020 CHINH DINH
Sewer availability Cleared 12/17/2020 CHINH DINH

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/3/2021 Approved ALEJANDRO DE ARTOLA
METHANE-Barrier 4/3/2021 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 4/3/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/14/2021 Partial Approval JOHN KLARIN
PLUMBING-Rough 4/14/2021 Partial Approval JOHN KLARIN
Insulation 4/21/2021 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/17/2021 Partial Approval JOHN KLARIN
Sewer 6/17/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 6/23/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 6/23/2021 Corrections Issued JOHN KLARIN
Green Building Rough 6/23/2021 Approved JOHN KLARIN
HVAC-Rough 6/23/2021 Approved JOHN KLARIN
METHANE-Rough 6/23/2021 Approved JOHN KLARIN
PLUMBING-Rough 6/23/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 6/25/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/25/2021 Approved JOHN KLARIN
HVAC-Rough 6/25/2021 Approved JOHN KLARIN
PLUMBING-Rough 6/25/2021 Approved JOHN KLARIN
Insulation 7/7/2021 Approved JOHN KLARIN
Drywall Nailing 7/14/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/14/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/15/2021 Approved JOHN KLARIN
Final 10/15/2021 Corrections Issued JOHN KLARIN
Green Building Final 10/15/2021 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 10/15/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 10/15/2021 Approved JOHN KLARIN
Final 11/24/2021 Corrections Issued JOHN KLARIN
Green Building Final 11/24/2021 Approved JOHN KLARIN
ELECTRICAL-Final 12/2/2021 Approved JOHN KLARIN
Final 12/2/2021 Corrections Issued JOHN KLARIN
Green Building Final 12/2/2021 Approved JOHN KLARIN
HVAC-Final 12/2/2021 Approved JOHN KLARIN
PLUMBING-Final 12/2/2021 Approved JOHN KLARIN
Final 12/8/2021 Corrections Issued JOHN KLARIN
Final 1/28/2022 OK to Issue CofO EUGENE CASSIDY