2120 W ELSINORE ST 90026

Certificate Information: 2120 W ELSINORE ST 90026

Application / Permit
19014-40000-06825
Plan Check / Job No.
B19SP01906
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of and one-story addition to (E) detached garage to create Accessory Dwelling Unit per SB229 and AB494. All work per Engineered Design.
Permit Issued
Issued on 3/8/2021
Issuing Office
Current Status
CofO Issued on 7/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 JASON JANGADA
Corrections Issued 12/31/2019 JASON JANGADA
Quality Review Completed 1/2/2020 CHRISTOPHER KOMANCHECK
Building Plans Picked Up 1/21/2020 APPLICANT
Green Plans Picked Up 2/3/2020 APPLICANT
Applicant returned to address corrections 3/11/2020 JASON JANGADA
Plan Check Approved 3/19/2020 JASON JANGADA
Issued 3/8/2021 APPLICANT
CofO in Progress 7/13/2022 THOMAS LOGRASSO
Permit Finaled 7/28/2022 DEROLD HAUFF
CofO Issued 7/28/2022 DEROLD HAUFF
Permit Finaled 7/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/14/2020 JEREMY CARTER
Green Code Cleared 2/27/2020 DONALD CRICHLOW
Address approval Cleared 3/11/2020 YEGANEH SADEGHI
Eng Process Fee Ord 176,300 Cleared 3/11/2020 YEGANEH SADEGHI
Grading Pre-Inspection Cleared 3/11/2020 JASON JANGADA
Roof/Waste drainage to street Cleared 3/11/2020 ERIK BEASLEY
Sewer availability Cleared 3/11/2020 YEGANEH SADEGHI
GPI Written Notices Cleared 3/17/2020 JASON JANGADA

Contact Information

Contractor Opus Builders Inc; Lic. No.: 1059646-B 213 N ORANGE STREET SUITE D      GLENDALE, CA 91203
Engineer Chu,, Tien Manh; Lic. No.: C72324 9542 PACIFIC AVE      ANAHEIM, CA 92804

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/15/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 3/15/2021 Partial Inspection SCOTT FINNILA
Underground Mechanical 1/10/2022 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 1/12/2022 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 1/13/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Partial Approval STUART CHAPMAN
Green Building Rough 1/28/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 2/14/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 2/14/2022 Corrections Issued THOMAS LOGRASSO
Green Building Rough 2/14/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 2/14/2022 Approved THOMAS LOGRASSO
PLUMBING-Rough 2/14/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 2/17/2022 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 2/17/2022 Approved THOMAS LOGRASSO
Insulation 2/17/2022 Corrections Issued THOMAS LOGRASSO
Drywall Nailing 3/7/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 3/7/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 3/7/2022 Partial Approval THOMAS LOGRASSO
Shower Pan 3/7/2022 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 3/7/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 3/9/2022 Approved THOMAS LOGRASSO
Drywall Nailing 3/9/2022 Approved THOMAS LOGRASSO
Shower Pan 3/9/2022 Approved THOMAS LOGRASSO
Sewer 5/9/2022 Partial Approval THOMAS LOGRASSO
Underground Mechanical 5/12/2022 Corrections Issued AMY COLIN
Final 6/8/2022 Corrections Issued THOMAS LOGRASSO
Green Building Final 6/8/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 6/8/2022 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 6/8/2022 Approved THOMAS LOGRASSO
Final 7/12/2022 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 7/12/2022 Approved THOMAS LOGRASSO