2921 S PACIFIC AVE 90731
Certificate Information: 2921 S PACIFIC AVE 90731
- Application / Permit
- 19014-40000-06524
- Plan Check / Job No.
- B19SP01837
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One-story, ground floor addition to the rear of (E) one-story Single Family Dwelling.
- Permit Issued
- Issued on 2/9/2021
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | MANUEL GARCIA |
| Corrections Issued | 12/17/2019 | MANUEL GARCIA |
| Quality Review Completed | 12/26/2019 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 12/27/2019 | APPLICANT |
| Applicant returned to address corrections | 6/10/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 10/7/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 12/8/2020 | MANUEL GARCIA |
| Building Plans Picked Up | 1/27/2021 | APPLICANT |
| Plan Check Approved | 2/2/2021 | MANUEL GARCIA |
| Issued | 2/9/2021 | APPLICANT |
| CofO in Progress | 1/19/2022 | ANSON MAGLASANG |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
| CofO Issued | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled | 1/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/6/2020 | ORVAL HERNANDEZ-MARCIAL |
| Address approval | Cleared | 3/11/2020 | YEGANEH SADEGHI |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2020 | YEGANEH SADEGHI |
| Roof/Waste drainage to street | Cleared | 3/11/2020 | YEGANEH SADEGHI |
| Sewer availability | Cleared | 3/11/2020 | YEGANEH SADEGHI |
| Construction near power lines | Cleared | 4/11/2020 | RIDWAN HARDY |
| Coastal Zone | Cleared | 4/22/2020 | KENTON TRINH |
| Specific Plan | Cleared | 4/23/2020 | KENTON TRINH |
| Green Code | Cleared | 6/3/2020 | MANUEL GARCIA |
| Green Code | Cleared | 6/3/2020 | RICHARD GARCIA |
| Grading Pre-Inspection | Cleared | 12/8/2020 | MANUEL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/19/2021 | Not Ready for Inspection | JOHN KLARIN |
| Pre-Inspection | 2/19/2021 | Approved | JOHN KLARIN |
| Grading Pre-Inspection | 3/3/2021 | Not Ready for Inspection | JOHN KLARIN |
| Footing/Foundation/Slab | 4/7/2021 | Approved | JOHN KLARIN |
| Wood Frame | 4/13/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/5/2021 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 5/5/2021 | Not Ready for Inspection | JOHN KLARIN |
| Insulation | 5/5/2021 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 5/5/2021 | Partial Approval | JOHN KLARIN |
| Sewer | 5/5/2021 | Partial Approval | JOHN KLARIN |
| Insulation | 5/10/2021 | Approved | JOHN KLARIN |
| Wood Frame | 6/2/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 7/6/2021 | Approved | JOHN KLARIN |
| HVAC-Rough | 7/6/2021 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 7/6/2021 | Approved | JOHN KLARIN |
| Rough-Elec/Plmb/HVAC | 7/6/2021 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/29/2021 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 7/29/2021 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 7/29/2021 | Approved | ANSON MAGLASANG |
| HVAC-Rough | 7/29/2021 | Approved | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 8/12/2021 | Partial Approval | CRAIG DAVIS |
| Drywall Nailing | 8/12/2021 | Partial Approval | CRAIG DAVIS |
| Interior/Exterior Lathing | 8/12/2021 | Approved | CRAIG DAVIS |
| ELECTRICAL-Rough | 9/14/2021 | Partial Approval | ANSON MAGLASANG |
| PLUMBING-Rough | 9/14/2021 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 10/15/2021 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Final | 10/15/2021 | Approved | ANSON MAGLASANG |
| Final | 10/15/2021 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 10/15/2021 | Approved | ANSON MAGLASANG |
| HVAC-Final | 10/15/2021 | Approved | ANSON MAGLASANG |
| PLUMBING-Final | 10/15/2021 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 10/15/2021 | SGSOV Not Ready | ANSON MAGLASANG |
| Smoke Detectors | 10/15/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Final | 10/22/2021 | Approved | ANSON MAGLASANG |
| Final | 10/22/2021 | Corrections Issued | ANSON MAGLASANG |
| HVAC-Final | 10/22/2021 | Approved | ANSON MAGLASANG |
| PLUMBING-Final | 10/22/2021 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 10/22/2021 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 10/22/2021 | Approved | ANSON MAGLASANG |
| Final | 1/18/2022 | OK to Issue CofO | ANSON MAGLASANG |