6133 W 75TH ST 90045
Certificate Information: 6133 W 75TH ST 90045
- Application / Permit
- 19014-40000-06430
- Plan Check / Job No.
- B19SP01823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Second story addition and exterior/ interior remodel on first floor with new patio cover.
- Permit Issued
- Issued on 10/22/2020
- Issuing Office
- Current Status
- CofO Issued on 12/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | MANUEL GARCIA |
| Corrections Issued | 12/24/2019 | MANUEL GARCIA |
| Quality Review Completed | 1/9/2020 | MARJAN SHENASI |
| Green Plans Picked Up | 1/27/2020 | APPLICANT |
| Applicant returned to address corrections | 6/18/2020 | MANUEL GARCIA |
| Applicant returned to address corrections | 8/20/2020 | MANUEL GARCIA |
| Plan Check Approved | 9/29/2020 | MANUEL GARCIA |
| Issued | 10/22/2020 | APPLICANT |
| Building Plans Picked Up | 10/28/2020 | APPLICANT |
| CofO in Progress | 12/21/2021 | DAVID FEILER |
| Permit Finaled | 12/23/2021 | DANIEL ORRANTE |
| CofO Issued | 12/23/2021 | DANIEL ORRANTE |
| Permit Finaled | 12/23/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/12/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 5/27/2020 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 6/18/2020 | MANUEL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 6/25/2020 | ANTHONY MAINEZ |
| Green Code | Cleared | 8/20/2020 | RICHARD GARCIA |
Contact Information
| Contractor | Lum Raymond Construction; Lic. No.: 720927-B | 4625 WEST 64TH STREET LOS ANGELES, CA 90043 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/30/2020 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/9/2020 | Corrections Issued | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 11/10/2020 | Partial Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 11/25/2020 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 12/1/2020 | Partial Approval | DAVID HEINE |
| Deputy Steel/Welding | 12/8/2020 | Conditional Approval | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 1/28/2021 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/25/2021 | Corrections Issued | DAVID HEINE |
| Green Building Rough | 2/25/2021 | Not Ready for Inspection | DAVID HEINE |
| Rough-Elec/Plmb/HVAC | 2/25/2021 | Approved | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 3/8/2021 | Corrections Issued | PIERRE VEGA |
| Interior/Exterior Lathing | 3/12/2021 | Partial Approval | DAVID HEINE |
| Shower Pan | 3/24/2021 | Approved | BRENDAN LOONEY |
| Insulation | 4/5/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 4/7/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 4/7/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 4/12/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 4/12/2021 | Approved | BRENDAN LOONEY |
| Insulation | 4/12/2021 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 4/19/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 5/20/2021 | Approved | BRENDAN LOONEY |
| Final | 10/4/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/4/2021 | Approved | BRENDAN LOONEY |
| Green Building Final | 10/4/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 10/4/2021 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 10/4/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 11/16/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 11/22/2021 | Approved | BOBBY KEY |
| HVAC-Final | 11/22/2021 | Approved | BOBBY KEY |
| PLUMBING-Final | 11/22/2021 | Approved | BOBBY KEY |
| Service/Power Release | 11/22/2021 | Approved | BOBBY KEY |
| Final | 12/13/2021 | Corrections Issued | DAVID FEILER |
| Green Building Final | 12/13/2021 | Approved | DAVID FEILER |
| Final | 12/21/2021 | OK to Issue CofO | DAVID FEILER |