8009 S NAYLOR AVE 90045

Certificate Information: 8009 S NAYLOR AVE 90045

Application / Permit
19014-40000-06037
Plan Check / Job No.
B19SP01711
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
One-story, ground floor addition (474.8 SF) to the side of (E) garage (360 SF) to create Accessory Dwelling Unit (474.8 SF) per SB229 and AB494 with attached garage (360 SF). All work per Engineered Design.
Permit Issued
Issued on 6/23/2021
Issuing Office
Current Status
CofO Issued on 5/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2019 APPLICANT
Building Plans Picked Up 11/13/2019 APPLICANT
Assigned to Plan Check Engineer 12/3/2019 KAVIAN REFAHI
Corrections Issued 12/4/2019 KAVIAN REFAHI
Quality Review Completed 12/11/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 12/13/2019 APPLICANT
Applicant returned to address corrections 3/5/2020 KAVIAN REFAHI
Applicant returned to address corrections 11/9/2020 KAVIAN REFAHI
Plan Check Approved 4/28/2021 KAVIAN REFAHI
Issued 6/23/2021 APPLICANT
CofO in Progress 5/22/2023 BOBBY KEY
Permit Finaled 5/30/2023 DANIEL ORRANTE
CofO Issued 5/30/2023 DANIEL ORRANTE
Permit Finaled 5/30/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/18/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 12/18/2019 THOMAS LANG
Sewer availability Cleared 12/18/2019 THOMAS LANG
Green Code Cleared 12/19/2019 DONALD CRICHLOW
Low Impact Development Cleared 10/23/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/10/2020 DINAH GARIN
Hold Cleared 10/4/2021 Yasaman Shayesteh

Contact Information

Contractor Zigner Ami General Contractor; Lic. No.: 493578-B PO BOX 6461      WOODLAND HILLS, CA 91365
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/7/2021 Corrections Issued BRENDAN LOONEY
Sewer 10/7/2021 Not Ready for Inspection BRENDAN LOONEY
Underground Mechanical 10/7/2021 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 10/13/2021 Partial Approval JOHNNY MIRANDA
Sewer 10/13/2021 Approved JOHNNY MIRANDA
Deputy Drilled-In Anchors 10/14/2021 Conditional Approval DEANDRE HOFFMAN
ELECTRICAL-Rough 12/20/2021 Approved BOBBY KEY
HVAC-Rough 12/20/2021 Approved BOBBY KEY
PLUMBING-Rough 12/20/2021 Approved BOBBY KEY
Wood Frame 12/20/2021 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 1/19/2022 Approved BOBBY KEY
Footing/Foundation/Slab 1/19/2022 Corrections Issued BOBBY KEY
Green Building Rough 1/19/2022 Approved BOBBY KEY
Insulation 1/19/2022 Approved BOBBY KEY
Interior/Exterior Lathing 1/19/2022 Partial Approval BOBBY KEY
Drywall Nailing 2/4/2022 Approved BOBBY KEY
Footing/Foundation/Slab 2/4/2022 Approved BOBBY KEY
Interior/Exterior Lathing 2/4/2022 Approved BOBBY KEY
Shower Pan 2/24/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 7/6/2022 Corrections Issued STEPHANIE SWANSON
Final 7/6/2022 Corrections Issued STEPHANIE SWANSON
Green Building Final 7/6/2022 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Final 7/6/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 7/6/2022 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 7/6/2022 SGSOV Not Ready STEPHANIE SWANSON
Service/Power Release 7/6/2022 Not Ready for Inspection STEPHANIE SWANSON
Smoke Detectors 7/6/2022 Approved STEPHANIE SWANSON
Final 8/25/2022 Not Ready for Inspection BOBBY KEY
Green Building Final 8/25/2022 Approved BOBBY KEY
HVAC-Final 8/25/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 8/25/2022 SGSOV Approved BOBBY KEY
ELECTRICAL-Final 5/22/2023 Approved BOBBY KEY
Final 5/22/2023 OK to Issue CofO BOBBY KEY
Service/Power Release 5/22/2023 Approved BOBBY KEY