13001 W MENLO AVE 90247
Certificate Information: 13001 W MENLO AVE 90247
- Application / Permit
- 19014-40000-05452
- Plan Check / Job No.
- B19SP01554
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- One-story ground floor addition (1,198 SF) to (E) one-story detached garage to create Accessory Dwelling Unit per SB229 and AB494 with two-car garage. All work per WFPP.
- Permit Issued
- Issued on 7/1/2020
- Issuing Office
- Current Status
- CofO Issued on 1/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 11/5/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 11/14/2019 | FELIX FIGUEROA |
| Green Plans Picked Up | 5/5/2020 | APPLICANT |
| Applicant returned to address corrections | 5/15/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 6/24/2020 | KAMRAN GHOTBI RAVANDI |
| Issued | 7/1/2020 | APPLICANT |
| Building Plans Picked Up | 7/1/2020 | APPLICANT |
| CofO in Progress | 1/14/2021 | ANSON MAGLASANG |
| Permit Finaled | 1/15/2021 | DEROLD HAUFF |
| CofO Issued | 1/15/2021 | DEROLD HAUFF |
| Permit Finaled | 1/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/8/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 1/8/2020 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 4/14/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/16/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 5/1/2020 | RICHARD GARCIA |
Contact Information
| Contractor | Frisco Investment Group Inc; Lic. No.: 1038932-B | 2851 W 120TH ST STE #E112 HAWTHORNE, CA 90250 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/14/2020 | Partial Approval | EUGENE CASSIDY |
| Pre-Inspection | 7/14/2020 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/20/2020 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 7/20/2020 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 7/20/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/27/2020 | Corrections Issued | JOHN KLARIN |
| Insulation | 7/29/2020 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 7/29/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Partial Approval | EUGENE CASSIDY |
| Insulation | 7/31/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/2/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/2/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 9/2/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 9/2/2020 | Approved | EUGENE CASSIDY |
| MERV13>=Rough | 9/2/2020 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 9/2/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/2/2020 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 9/3/2020 | Approved | EUGENE CASSIDY |
| Wood Frame | 9/3/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/11/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 9/11/2020 | Approved | EUGENE CASSIDY |
| Insulation | 9/11/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/11/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 9/17/2020 | Approved | EUGENE CASSIDY |
| Sewer | 10/26/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/17/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 12/17/2020 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 12/17/2020 | Approved | EUGENE CASSIDY |
| Green Building Final | 12/17/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 12/17/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| MERV13>=Final | 12/17/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 12/17/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/17/2020 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 12/17/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/7/2021 | Approved | EUGENE CASSIDY |
| Final | 1/7/2021 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 1/7/2021 | Approved | EUGENE CASSIDY |
| Green Building Final | 1/7/2021 | Approved | EUGENE CASSIDY |
| HVAC-Final | 1/7/2021 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 1/7/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/7/2021 | Approved | EUGENE CASSIDY |
| Service/Power Release | 1/7/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/12/2021 | Approved | EUGENE CASSIDY |
| Final | 1/12/2021 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 1/12/2021 | Approved | EUGENE CASSIDY |