5442 W 76TH ST 90045
Certificate Information: 5442 W 76TH ST 90045
- Application / Permit
- 19014-40000-05322
- Plan Check / Job No.
- B19SP01508
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND MAJOR REMODEL TO EXISTING 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED GARAGE, EQUIPPED THROUGHOUT WITH NFPA13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 7/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | SERGIO SILVA |
| Green Plans Picked Up | 10/28/2019 | APPLICANT |
| Corrections Issued | 11/5/2019 | SERGIO SILVA |
| Quality Review Completed | 11/14/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/13/2019 | SERGIO SILVA |
| Plan Check Approved | 12/20/2019 | SERGIO SILVA |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 6/30/2021 | BRENDAN LOONEY |
| Permit Finaled | 7/16/2021 | VINCENT COTTON |
| CofO Issued | 7/16/2021 | VINCENT COTTON |
| Permit Finaled | 7/16/2021 | VINCENT COTTON |
Permit Application Clearance Information
| CPC | Cleared | 12/4/2019 | TERRI OSBORNE |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2019 | PHILLIP WILSON |
| Grading Pre-Inspection | Cleared | 12/5/2019 | JONATHAN HOM |
| Permit | Cleared | 12/5/2019 | PHILLIP WILSON |
| Roof/Waste drainage to street | Cleared | 12/5/2019 | PHILLIP WILSON |
| Sewer availability | Cleared | 12/5/2019 | PHILLIP WILSON |
| Low Impact Development | Cleared | 12/17/2019 | ORVAL HERNANDEZ-MARCIAL |
| Green Code | Cleared | 12/18/2019 | DONALD CRICHLOW |
Contact Information
| Contractor | Harvey Ralph Donell; Lic. No.: 652651-B | 11715 SOUTH WILTON PLACE HAWTHORNE, CA 90250 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/27/2020 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/7/2020 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 4/14/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 4/14/2020 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 4/17/2020 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/17/2020 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/17/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 4/17/2020 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 4/24/2020 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 4/24/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 4/24/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 4/24/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 4/24/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2020 | Partial Approval | DAVID FEILER |
| Shower Pan | 4/29/2020 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 6/4/2020 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/4/2020 | Corrections Issued | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 6/4/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 6/4/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 6/10/2020 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 6/10/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Rough | 6/10/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/17/2020 | Partial Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/23/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 6/23/2020 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 6/23/2020 | Approved | JUAN VALENZUELA |
| Insulation | 6/23/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/23/2020 | Partial Approval | JUAN VALENZUELA |
| MERV13>=Rough | 6/23/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 6/23/2020 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 6/26/2020 | Approved | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 8/13/2020 | Partial Inspection | JUAN VALENZUELA |
| Final | 9/2/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 9/2/2020 | Corrections Issued | JUAN VALENZUELA |
| MERV13>=Final | 9/2/2020 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 9/2/2020 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 9/2/2020 | Corrections Issued | JUAN VALENZUELA |
| Final | 9/11/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Final | 9/11/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Final | 9/11/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 9/11/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 10/22/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 10/22/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| MERV13>=Final | 10/22/2020 | Approved | JUAN VALENZUELA |
| Smoke Detectors | 10/22/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 11/16/2020 | Approved | JUAN VALENZUELA |
| Final | 11/16/2020 | Partial Approval | JUAN VALENZUELA |
| Green Building Final | 11/16/2020 | Approved | JUAN VALENZUELA |
| HVAC-Final | 11/16/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 11/16/2020 | Approved | JUAN VALENZUELA |
| Service/Power Release | 11/16/2020 | Approved | JUAN VALENZUELA |
| Final | 6/29/2021 | OK to Issue CofO | BRENDAN LOONEY |