5241 E BUCHANAN ST 90042

Certificate Information: 5241 E BUCHANAN ST 90042

Application / Permit
19014-40000-04559
Plan Check / Job No.
B19SP01351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One-story, ground floor additions (651 SF total) and remodel of (E) one-story Single Family Dwelling to create new entry porch at front (153 SF) and kitchen expansion and new bedroom/bathroom at rear (498 SF). All work per engineered design.
Permit Issued
Issued on 8/6/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2019 APPLICANT
Assigned to Plan Check Engineer 9/19/2019 JASON JANGADA
Corrections Issued 9/26/2019 JASON JANGADA
Quality Review Completed 10/3/2019 CHRISTOPHER KOMANCHECK
Applicant returned to address corrections 2/27/2020 JASON JANGADA
Green Plans Picked Up 6/19/2020 APPLICANT
Applicant returned to address corrections 7/14/2020 JASON JANGADA
Plan Check Approved 7/22/2020 JASON JANGADA
Building Plans Picked Up 7/22/2020 APPLICANT
Issued 8/6/2020 APPLICANT
CofO in Progress 9/23/2021 CRAIG VAUGHAN
Permit Finaled 12/13/2021 DEROLD HAUFF
CofO Issued 12/13/2021 DEROLD HAUFF
Permit Finaled 12/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/5/2019 ERIK BEASLEY
Grading Pre-Inspection Cleared 11/5/2019 KIRK LINKLATER
Low Impact Development Cleared 2/7/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/7/2020 JEANIE LAM
Green Code Cleared 2/13/2020 RICHARD GARCIA
GPI Written Notices Cleared 2/19/2020 JASON JANGADA

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/14/2020 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 9/14/2020 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/22/2020 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/2/2020 Corrections Issued CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/19/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 10/19/2020 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 10/21/2020 Partial Approval CRAIG VAUGHAN
Insulation 10/21/2020 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 11/25/2020 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 12/2/2020 Approved CRAIG VAUGHAN
Pre-Inspection 1/5/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 3/1/2021 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/1/2021 Partial Approval CRAIG VAUGHAN
Shower Pan 3/1/2021 Approved CRAIG VAUGHAN
Wood Frame 3/1/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/5/2021 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 3/5/2021 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 3/5/2021 Approved ENRIQUE MIRELES
HVAC-Rough 3/5/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 3/11/2021 Approved OSVALDO PARAMO
HVAC-Rough 3/11/2021 Approved OSVALDO PARAMO
Wood Frame 3/11/2021 Not Ready for Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 3/17/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 3/17/2021 Approved CRAIG VAUGHAN
Shower Pan 3/17/2021 Approved CRAIG VAUGHAN
Insulation 3/23/2021 Approved CRAIG VAUGHAN
Drywall Nailing 4/5/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/5/2021 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 4/14/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 6/3/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 6/11/2021 Not Ready for Inspection COREY HUPP
ELECTRICAL-Final 6/18/2021 Partial Approval CRAIG VAUGHAN
Service/Power Release 6/18/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 8/18/2021 Approved CRAIG VAUGHAN
Final 8/18/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 8/18/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Final 8/18/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 8/18/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/18/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 8/18/2021 Approved CRAIG VAUGHAN
Final 8/25/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 8/25/2021 Corrections Issued CRAIG VAUGHAN
Final 9/16/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2021 Approved CRAIG VAUGHAN
Green Building Final 9/16/2021 Approved CRAIG VAUGHAN
HVAC-Final 9/16/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 9/16/2021 Approved CRAIG VAUGHAN
Final 9/22/2021 OK to Issue CofO CRAIG VAUGHAN