17328 W STAGG ST 91325
Certificate Information: 17328 W STAGG ST 91325
- Application / Permit
- 19014-40000-04429
- Plan Check / Job No.
- B19SP01317
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One-story, irregular-shaped ground floor addition to the rear of (E) one-story Single Family Dwelling with attached garage. EXTENSION OF GARAGE FOR STORAGE. AND PATIO ADDITON AT REAR. All work per engineered design.
- Permit Issued
- Issued on 10/1/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2019 | MONICA RAMIREZ |
| Corrections Issued | 9/18/2019 | MONICA RAMIREZ |
| Quality Review Completed | 9/26/2019 | HERNAN ARREOLA |
| Green Plans Picked Up | 9/27/2019 | APPLICANT |
| Applicant returned to address corrections | 5/1/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/9/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 5/25/2021 | MONICA RAMIREZ |
| Plan Check Approved | 9/7/2021 | MONICA RAMIREZ |
| Building Plans Picked Up | 9/27/2021 | APPLICANT |
| Issued | 10/1/2021 | APPLICANT |
| CofO in Progress | 2/28/2023 | RAUL OLAGI |
| CofO Issued | 3/6/2023 | MICHAEL SMITH |
| Permit Finaled | 3/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 10/30/2019 | DONALD CRICHLOW |
| Sewer availability | Cleared | 10/30/2019 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 3/12/2020 | ORVAL HERNANDEZ-MARCI |
| Miscellaneous | Cleared | 5/25/2021 | MONICA RAMIREZ |
| Roof/Waste drainage to street | Cleared | 6/7/2021 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 8/4/2021 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/13/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Pre-Inspection | 10/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 10/26/2021 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 11/22/2021 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 11/30/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2021 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 12/20/2021 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/21/2021 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 12/21/2021 | Partial Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2021 | Partial Approval | RAUL OLAGI |
| Pre-Inspection | 1/31/2022 | Partial Approval | RAUL OLAGI |
| Deputy Drilled-In Anchors | 2/9/2022 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 2/16/2022 | Partial Approval | RAUL OLAGI |
| Deputy Wood Construction | 3/30/2022 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 6/28/2022 | Corrections Issued | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 9/12/2022 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/16/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 9/16/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 9/16/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 9/16/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 9/16/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 9/16/2022 | Approved | RAUL OLAGI |
| Insulation | 9/27/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 9/27/2022 | Not Ready for Inspection | RAUL OLAGI |
| Drywall Nailing | 10/4/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 10/4/2022 | Approved | RAUL OLAGI |
| Shower Pan | 10/4/2022 | Approved | RAUL OLAGI |
| Final | 2/6/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 2/6/2023 | Approved | RAUL OLAGI |
| Green Building Final | 2/6/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/6/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 2/6/2023 | Approved | RAUL OLAGI |
| Final | 2/28/2023 | OK to Issue CofO | RAUL OLAGI |
| Service/Power Release | 2/28/2023 | Approved | RAUL OLAGI |