11222 W HOMEDALE ST 90049

Certificate Information: 11222 W HOMEDALE ST 90049

Application / Permit
19014-40000-03997
Plan Check / Job No.
B19SP01156
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Second story addition (356 SF) over (E) garage to create Accessory Dwelling Unit per SB229 and AB494. All work per engineered design.
Permit Issued
Issued on 9/16/2020
Issuing Office
Current Status
Issued on 9/16/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/24/2019 APPLICANT
Assigned to Plan Check Engineer 8/8/2019 JASON JANGADA
Corrections Issued 8/12/2019 JASON JANGADA
Green Plans Picked Up 8/14/2019 APPLICANT
Quality Review Completed 8/16/2019 CHRISTOPHER KOMANCHECK
Building Plans Picked Up 8/21/2019 APPLICANT
Plan Check Approved 10/30/2019 JASON JANGADA
Issued 9/16/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/4/2019 ERIK BEASLEY
Roof/Waste drainage to street Cleared 9/4/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 9/6/2019 JAMES MORALEZ
Sewer availability Cleared 9/6/2019 JAMES MORALEZ
Green Code Cleared 10/3/2019 DONALD CRICHLOW
Grading Pre-Inspection Cleared 10/23/2019 PATRICK MISCHLICH

Contact Information

Contractor West Coast Quality Construction; Lic. No.: 871102-B 11825 LAURELWOOD DRIVE #5      STUDIO CITY, CA 91604
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/18/2020 Not Ready for Inspection CARLOS MATAMOROS
Sewer 9/18/2020 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 9/21/2020 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 9/21/2020 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 9/22/2020 Approved CARLOS MATAMOROS
Sewer 9/22/2020 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 3/24/2021 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 3/25/2021 Partial Approval CARLOS MATAMOROS
Underground Mechanical 3/25/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 2/28/2022 Not Ready for Inspection CARLOS MATAMOROS
Deputy Wood Construction 2/28/2022 Conditional Approval CARLOS MATAMOROS
Green Building Rough 2/28/2022 Not Ready for Inspection CARLOS MATAMOROS
MERV13>=Rough 2/28/2022 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Conditional Approval CARLOS MATAMOROS