11930 1/2 W COVELLO ST 91605

Certificate Information: 11930 1/2 W COVELLO ST 91605

Application / Permit
19014-40000-03439
Plan Check / Job No.
B19SP01023
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert garage to accessory dwelling unit and add 165 SF per AB 494 and SB229. All work per engineered design.
Permit Issued
Issued on 9/19/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 JASON JANGADA
Corrections Issued 7/15/2019 JASON JANGADA
Quality Review Completed 7/15/2019 CHRISTOPHER KOMANCHECK
Building Plans Picked Up 7/18/2019 APPLICANT
Green Plans Picked Up 7/25/2019 APPLICANT
Applicant returned to address corrections 8/9/2019 JASON JANGADA
Plan Check Approved 9/5/2019 JASON JANGADA
Issued 9/19/2019 LADBS
CofO in Progress 8/10/2022 CALEB MEISTER
Permit Finaled 8/13/2022 DANIEL ORRANTE
CofO Issued 8/13/2022 DANIEL ORRANTE
Permit Finaled 8/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/25/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/25/2019 CELINA MORENO
Roof/Waste drainage to street Cleared 7/25/2019 CELINA MORENO
Sewer availability Cleared 7/25/2019 CELINA MORENO
Construction near power lines Cleared 7/29/2019 WALTER RAMIREZ
Green Code Cleared 8/6/2019 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Mohammad Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2019 Corrections Issued MISAEL ESPARZA
Sewer 10/17/2019 Approved MISAEL ESPARZA
Footing/Foundation/Slab 10/29/2019 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 12/31/2019 Approved RAYMOND KEHOE
ELECTRICAL-Rough 12/31/2019 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 12/31/2019 Partial Approval RAYMOND KEHOE
Green Building Rough 12/31/2019 Approved RAYMOND KEHOE
Pre-Inspection 12/31/2019 Corrections Issued RAYMOND KEHOE
Gas Test 4/20/2020 Not Ready for Inspection GREGG CUMMINGS
Insulation 4/20/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 4/20/2020 Approved GREGG CUMMINGS
Drywall Nailing 5/6/2020 Approved RAYMOND KEHOE
Interior/Exterior Lathing 5/6/2020 Partial Approval RAYMOND KEHOE
Shower Pan 6/29/2020 Not Ready for Inspection PIERRE VEGA
Shower Pan 7/10/2020 Approved RAYMOND KEHOE
Gas Test 11/16/2020 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 3/19/2021 SGSOV Not Ready DANIEL DREW
Pre-Inspection 3/24/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 4/1/2021 SGSOV Not Ready DANIEL DREW
Final 4/20/2021 Not Ready for Inspection DANIEL DREW
Green Building Final 4/20/2021 Corrections Issued DANIEL DREW
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 4/20/2021 Approved DANIEL DREW
Final 6/9/2021 Corrections Issued JOHN HAYES
Green Building Final 6/9/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 5/12/2022 Approved MISAEL ESPARZA
Final 5/12/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 5/12/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 5/12/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 5/12/2022 Approved MISAEL ESPARZA
Service/Power Release 5/12/2022 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 6/24/2022 Not Ready for Inspection JOHN HAYES
Final 6/24/2022 Not Ready for Inspection JOHN HAYES
Green Building Final 6/24/2022 Not Ready for Inspection JOHN HAYES
HVAC-Final 6/24/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 6/24/2022 Not Ready for Inspection JOHN HAYES
Final 8/1/2022 Not Ready for Inspection CALEB MEISTER
Green Building Final 8/1/2022 Not Ready for Inspection CALEB MEISTER
Final 8/8/2022 OK to Issue CofO CALEB MEISTER
Green Building Final 8/8/2022 Approved CALEB MEISTER