18033 W SWEET ELM DR 91316

Certificate Information: 18033 W SWEET ELM DR 91316

Application / Permit
19014-40000-03364
Plan Check / Job No.
B19SP00988
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Proposed second story (18'-6" x 31'-1") and ground floor (4'-11" x 20'-9") addition to existing single family dwelling ground floor addition will extend existing kitchen and second story addiiton will 1 new bedroom and extend existing master bedroom. Scope will also include the converion of existing covered patio to habitable area, add new irregular trellis at rear (38'-3" x 16'-3") , and major interior remodel (1900 SF). All work per engineered design.
Permit Issued
Issued on 11/14/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2019 APPLICANT
Green Plans Picked Up 7/12/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 MICHAEL LOPEZ
Corrections Issued 7/23/2019 MICHAEL LOPEZ
Quality Review Completed 7/27/2019 STANLEY RAAP
Building Plans Picked Up 8/1/2019 APPLICANT
Applicant returned to address corrections 9/5/2019 MICHAEL LOPEZ
Plan Check Approved 11/14/2019 MICHAEL LOPEZ
Issued 11/14/2019 LADBS
CofO in Progress 8/10/2021 DAVID SANDOVAL
Permit Finaled 2/18/2023 DANIEL ORRANTE
CofO Issued 2/18/2023 DANIEL ORRANTE
Permit Finaled 2/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/4/2019 JEANETTE VONG
Sewer availability Cleared 9/4/2019 JEANETTE VONG
Grading Pre-Inspection Cleared 9/12/2019 TIMOTHY POWELL
Green Code Cleared 10/17/2019 DONALD CRICHLOW
Low Impact Development Cleared 11/8/2019 RYAN HUDSON
GPI Written Notices Cleared 11/14/2019 ALEXANDER ANDREWS
Roof/Waste drainage to street Cleared 11/14/2019 THOMAS LANG

Contact Information

Contractor C A A General Contractor; Lic. No.: 696570-B 5901 COLFAX AVE      NORTH HOLLYWOOD, CA 91601
Engineer Kim,, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/11/2020 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 2/11/2020 Partial Approval DAVID SANDOVAL
Verify Sprinkler Sign Off 2/11/2020 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 3/2/2020 Approved DAVID SANDOVAL
Deputy Reinf. Concrete 3/4/2020 Approved DAVID SANDOVAL
PLUMBING-Rough 3/6/2020 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/22/2020 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval RONALD COWAN
Green Building Rough 4/22/2020 Not Ready for Inspection RONALD COWAN
Verify Sprinkler Sign Off 4/22/2020 Not Ready for Inspection RONALD COWAN
HVAC-Rough 6/3/2020 Approved DAVID SANDOVAL
PLUMBING-Rough 6/9/2020 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 6/15/2020 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Inspection DAVID SANDOVAL
PLUMBING-Rough 6/17/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Approved VINCENT HANLEY
Shower Pan 6/22/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 6/25/2020 Approved DAVID SANDOVAL
Shower Pan 6/25/2020 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 6/30/2020 Corrections Issued MICHAEL TEMPLE
Green Building Rough 6/30/2020 Not Ready for Inspection MICHAEL TEMPLE
Verify Sprinkler Sign Off 6/30/2020 Not Ready for Inspection MICHAEL TEMPLE
Interior/Exterior Lathing 7/20/2020 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 11/23/2020 Approved DAVID SANDOVAL
Green Building Rough 11/23/2020 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 11/23/2020 Approved DAVID SANDOVAL
Insulation 12/3/2020 Approved TROY SANDERS
Drywall Nailing 12/9/2020 Approved DAVID SANDOVAL
Gas Test 3/5/2021 Approved DAVID SANDOVAL
ELECTRICAL-Final 4/13/2021 Not Ready for Inspection DAVID SANDOVAL
Final 4/13/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 4/13/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Final 4/13/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Final 4/13/2021 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 4/13/2021 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 4/13/2021 Approved DAVID SANDOVAL
Structural Steel Frame 4/13/2021 Approved DAVID SANDOVAL
ELECTRICAL-Final 5/17/2021 Approved DAVID SANDOVAL
PLUMBING-Final 5/17/2021 Approved DAVID SANDOVAL
Green Building Final 5/24/2021 Approved DAVID SANDOVAL
HVAC-Final 5/24/2021 Approved DAVID SANDOVAL
Final 8/9/2021 OK to Issue CofO DAVID SANDOVAL