4844 N WILLOW CREST AVE 91601
Certificate Information: 4844 N WILLOW CREST AVE 91601
- Application / Permit
- 19014-40000-02667
- Plan Check / Job No.
- B19SP00792
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One-story, irregular-shaped, ground floor additions to the front and rear of (E) one-story SFD. All work per engineered design. (1 of 2)
- Permit Issued
- Issued on 12/16/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | JASON JANGADA |
| Corrections Issued | 6/21/2019 | JASON JANGADA |
| Quality Review Completed | 6/28/2019 | CHRISTOPHER KOMANCHECK |
| Building Plans Picked Up | 7/16/2019 | APPLICANT |
| Green Plans Picked Up | 8/9/2019 | APPLICANT |
| Applicant returned to address corrections | 8/28/2019 | JASON JANGADA |
| Applicant returned to address corrections | 11/4/2019 | JASON JANGADA |
| Plan Check Approved | 11/14/2019 | JASON JANGADA |
| Issued | 12/16/2019 | LADBS |
| CofO in Progress | 8/15/2022 | THOMAS FINNILA |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
| CofO Issued | 9/3/2022 | MICHAEL SMITH |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/28/2019 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2019 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 10/30/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 10/30/2019 | ANTHONY MAINEZ |
| Green Code | Cleared | 11/6/2019 | RICHARD GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/12/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/5/2020 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 8/12/2020 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 9/8/2020 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/30/2020 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/30/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 10/30/2020 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 10/30/2020 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 11/16/2020 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 11/16/2020 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 11/16/2020 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 11/16/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 12/18/2020 | Approved | BEAU COLLINS |
| Interior/Exterior Lathing | 12/18/2020 | Partial Approval | BEAU COLLINS |
| Wood Frame | 12/18/2020 | Approved | BEAU COLLINS |
| Insulation | 1/19/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 2/16/2021 | Approved | BEAU COLLINS |
| Green Building Rough | 2/16/2021 | Approved | BEAU COLLINS |
| Shower Pan | 6/25/2021 | Approved | THOMAS FINNILA |
| Gas Test | 3/10/2022 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Final | 3/10/2022 | Approved | RYAN SALAZAR |
| Gas Test | 3/15/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 3/23/2022 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 7/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 7/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 7/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 7/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/25/2022 | Approved | THOMAS FINNILA |
| Final | 7/25/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/25/2022 | Approved | THOMAS FINNILA |
| Green Building Final | 7/25/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 7/25/2022 | Approved | THOMAS FINNILA |
| Final | 8/12/2022 | OK to Issue CofO | THOMAS FINNILA |