875 W 24TH ST 90731

Certificate Information: 875 W 24TH ST 90731

Application / Permit
19014-40000-02648
Plan Check / Job No.
B19SP00783
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and roof deck to (E) SFD, new attached 1-car garage.
Permit Issued
Issued on 10/4/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2019 APPLICANT
Green Plans Picked Up 6/20/2019 APPLICANT
Assigned to Plan Check Engineer 6/26/2019 MANUEL GARCIA
Corrections Issued 7/18/2019 MANUEL GARCIA
Quality Review Completed 7/25/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 7/30/2019 APPLICANT
Applicant returned to address corrections 9/20/2019 MANUEL GARCIA
Plan Check Approved 10/4/2019 MANUEL GARCIA
Issued 10/4/2019 LADBS
CofO in Progress 4/19/2024 JAMES CHAVEZ
Permit Finaled 4/19/2024 ANSON MAGLASANG
CofO Issued 4/19/2024 ANSON MAGLASANG
Permit Finaled 4/19/2024 ANSON MAGLASANG

Permit Application Clearance Information

Low Impact Development Cleared 8/15/2019 ORVAL HERNANDEZ-MARCI
Construction near power lines Cleared 8/20/2019 NADER ISKANDER
Encroachment in public way Cleared 8/20/2019 PHILLIP WILSON
Eng Process Fee Ord 176,300 Cleared 8/20/2019 DENNIS BRAGIN
Frnt yard landscape/Water mgmt Cleared 8/20/2019 SARAH GOLDMAN
Highway dedication Cleared 8/20/2019 PHILLIP WILSON
Miscellaneous Cleared 8/20/2019 SARAH GOLDMAN
Permit Cleared 8/20/2019 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 8/20/2019 DENNIS BRAGIN
Sewer availability Cleared 8/20/2019 DENNIS BRAGIN
Green Code Cleared 10/1/2019 RICHARD GARCIA
Grading Pre-Inspection Cleared 10/2/2019 MANUEL GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Von, Allworden, Brian Kent; Lic. No.: C52900 9160 S RURAL RD      TEMPE, AZ 85284

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/26/2020 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 5/26/2020 Not Ready for Inspection JOHN KLARIN
Pre-Inspection 5/26/2020 Not Ready for Inspection JOHN KLARIN
Sewer 6/26/2020 Corrections Issued JOHN KLARIN
Underground Mechanical 6/26/2020 Not Ready for Inspection JOHN KLARIN
Excavation/Setback/Form/Re-Bar 7/1/2020 Approved JOHN KLARIN
Sewer 7/1/2020 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 7/21/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/13/2020 Not Ready for Inspection JOHN KLARIN
Green Building Rough 8/13/2020 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 9/24/2020 Partial Inspection JOHN KLARIN
Green Building Rough 9/24/2020 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 10/2/2020 Conditional Approval JOHN KLARIN
Green Building Rough 10/2/2020 Not Ready for Inspection JOHN KLARIN
Drywall Nailing 12/28/2020 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 12/28/2020 Approved JOHN KLARIN
Gas Test 12/28/2020 Approved JOHN KLARIN
PLUMBING-Rough 12/28/2020 Approved JOHN KLARIN
Service/Power Release 12/28/2020 Not Ready for Inspection JOHN KLARIN
Service/Power Release 1/8/2021 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 1/13/2021 Approved JOHN KLARIN
Green Building Rough 1/13/2021 Approved JOHN KLARIN
Drywall Nailing 2/19/2021 Approved JOHN KLARIN
Service/Power Release 5/27/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 8/4/2021 Approved ANSON MAGLASANG
Insulation 8/4/2021 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 8/4/2021 Partial Approval ANSON MAGLASANG
Wood Frame 8/4/2021 Partial Approval ANSON MAGLASANG
Drywall Nailing 8/27/2021 Partial Approval ANSON MAGLASANG
Interior/Exterior Lathing 9/1/2021 Partial Approval ANSON MAGLASANG
ELECTRICAL-Rough 11/4/2021 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 11/4/2021 Partial Approval ANSON MAGLASANG
Shower Pan 11/4/2021 Partial Approval ANSON MAGLASANG
Interior/Exterior Lathing 11/12/2021 Partial Approval ANSON MAGLASANG
ELECTRICAL-Final 1/3/2024 Approved ANSON MAGLASANG
Final 1/3/2024 Corrections Issued ANSON MAGLASANG
Footing/Foundation/Slab 1/3/2024 Approved ANSON MAGLASANG
Green Building Final 1/3/2024 Approved ANSON MAGLASANG
HVAC-Final 1/3/2024 Approved ANSON MAGLASANG
PLUMBING-Final 1/3/2024 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Approved ANSON MAGLASANG
Smoke Detectors 1/3/2024 Approved ANSON MAGLASANG
Final 2/22/2024 Corrections Issued EUGENE CASSIDY
Final 4/18/2024 OK to Issue CofO JAMES CHAVEZ