964 W 10TH ST 90731
Certificate Information: 964 W 10TH ST 90731
- Application / Permit
- 19014-40000-02522
- Plan Check / Job No.
- B19SP00756
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One-story, irregular-shaped ground floor addition (456 SF) to the rear of (E) one-story Single Family Dwelling to create new bedroom and bathroom. All work per engineered design.
- Permit Issued
- Issued on 10/8/2019
- Issuing Office
- San Pedro
- Current Status
- Issued on 10/8/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2019 | CHRISTOPHER KOMANCHECK |
| Corrections Issued | 5/13/2019 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 6/14/2019 | CHRISTOPHER KOMANCHECK |
| Applicant returned to address corrections | 10/8/2019 | CHRISTOPHER KOMANCHECK |
| Plan Check Approved | 10/8/2019 | JASON JANGADA |
| Issued | 10/8/2019 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2019 | ALINE MILLER |
| Roof/Waste drainage to street | Cleared | 5/13/2019 | ALINE MILLER |
| Sewer availability | Cleared | 5/13/2019 | ALINE MILLER |
| Grading Pre-Inspection | Cleared | 6/20/2019 | JONATHAN HOM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/4/2020 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 2/4/2020 | No Access for Inspection | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 2/5/2020 | Corrections Issued | ANSON MAGLASANG |
| PLUMBING-Final | 4/3/2020 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 4/15/2020 | Partial Inspection | JOHN KLARIN |
| Green Building Rough | 4/15/2020 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Final | 4/15/2020 | Partial Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 7/29/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/29/2020 | Approved | JOHN KLARIN |
| Wood Frame | 7/29/2020 | Approved | JOHN KLARIN |
| Insulation | 8/10/2020 | Approved | JOHN KLARIN |
| Drywall Nailing | 8/12/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 8/12/2020 | Not Ready for Inspection | JOHN KLARIN |
| Drywall Nailing | 8/17/2020 | Approved | JOHN KLARIN |
| Green Building Rough | 8/17/2020 | Approved | JOHN KLARIN |
| Special/Order Compliance | 1/9/2025 | No Access for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/3/2025 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/3/2025 | Approved | JOSEPH MCGARRY |
| Final | 2/3/2025 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/3/2025 | Approved | JOSEPH MCGARRY |
| Green Building Final | 2/3/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 2/3/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 12/1/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 12/1/2025 | Approved | JOSEPH MCGARRY |