1915 1/2 E 114TH ST 90059
Certificate Information: 1915 1/2 E 114TH ST 90059
- Application / Permit
- 19014-40000-02079
- Plan Check / Job No.
- B19SP00650
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Second Story addition (180 SF) and two-story ground-floor addition (408 SF total) to (E) garage to create Accessory Dwelling Unit per SB229 and AB494 (588 SF) with garage on first floor. All work per engineered design. "COMPLY WITH DEPARTMENT ORDER effective date 02/20/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 2/7/2020
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 10/8/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2019 | APPLICANT |
| Green Plans Picked Up | 5/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2019 | JASON JANGADA |
| Corrections Issued | 5/7/2019 | MUKUL GUPTA |
| Quality Review Completed | 5/14/2019 | CHRISTOPHER KOMANCHECK |
| Building Plans Picked Up | 5/20/2019 | APPLICANT |
| Applicant returned to address corrections | 10/8/2019 | JASON JANGADA |
| Applicant returned to address corrections | 10/23/2019 | JASON JANGADA |
| Applicant returned to address corrections | 11/8/2019 | JASON JANGADA |
| Plan Check Approved | 11/19/2019 | JASON JANGADA |
| Issued | 2/7/2020 | LADBS |
| CofO in Progress | 10/7/2020 | KEITH EDGHILL |
| CofO in Progress | 10/7/2020 | KEITH EDGHILL |
| Permit Finaled | 10/8/2020 | BRUCE TODD |
| CofO Issued | 10/8/2020 | BRUCE TODD |
| Permit Finaled | 10/8/2020 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2019 | PHILLIP WILSON |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2019 | PHILLIP WILSON |
| Roof/Waste drainage to street | Cleared | 9/25/2019 | PHILLIP WILSON |
| Sewer availability | Cleared | 9/25/2019 | PHILLIP WILSON |
| Green Code | Cleared | 10/3/2019 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 10/7/2019 | MITESH PATEL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gunal,, Nezih M; Lic. No.: C18689 | 5474 GARFORD ST LONG BEACH, CA 90815 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/11/2020 | Approved | KEITH EDGHILL |
| Deputy Drilled-In Anchors | 2/14/2020 | Conditional Approval | KEITH EDGHILL |
| Excavation/Setback/Form/Re-Bar | 2/19/2020 | Approved | KEITH EDGHILL |
| Footing/Foundation/Slab | 2/19/2020 | Approved | KEITH EDGHILL |
| BUILDING-Rough-Frame | 3/11/2020 | Conditional Approval | KEITH EDGHILL |
| Green Building Rough | 3/11/2020 | Conditional Approval | KEITH EDGHILL |
| BUILDING-Rough-Frame | 3/31/2020 | Approved | KEITH EDGHILL |
| ELECTRICAL-Rough | 3/31/2020 | Approved | KEITH EDGHILL |
| Green Building Rough | 3/31/2020 | Approved | KEITH EDGHILL |
| PLUMBING-Rough | 3/31/2020 | Approved | KEITH EDGHILL |
| Deputy Wood Construction | 4/1/2020 | Conditional Approval | PAUL BECKER |
| Insulation | 4/7/2020 | Approved | KEITH EDGHILL |
| Drywall Nailing | 4/15/2020 | Approved | KEITH EDGHILL |
| Interior/Exterior Lathing | 4/15/2020 | Approved | KEITH EDGHILL |
| Interior/Exterior Lathing | 4/21/2020 | Approved | KEITH EDGHILL |
| Shower Pan | 4/21/2020 | Approved | KEITH EDGHILL |
| Gas Test | 5/7/2020 | Approved | KEITH EDGHILL |
| PLUMBING-Final | 5/7/2020 | Approved | KEITH EDGHILL |
| ELECTRICAL-Final | 6/16/2020 | Corrections Issued | KEITH EDGHILL |
| Final | 6/16/2020 | Corrections Issued | KEITH EDGHILL |
| Green Building Final | 6/16/2020 | Corrections Issued | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 6/16/2020 | SGSOV Not Ready | KEITH EDGHILL |
| Service/Power Release | 6/16/2020 | Corrections Issued | KEITH EDGHILL |
| Smoke Detectors | 6/16/2020 | Not Ready for Inspection | KEITH EDGHILL |
| ELECTRICAL-Final | 7/24/2020 | Corrections Issued | KEITH EDGHILL |
| Final | 7/24/2020 | Not Ready for Inspection | KEITH EDGHILL |
| Green Building Final | 7/24/2020 | Corrections Issued | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 7/24/2020 | SGSOV Not Ready | KEITH EDGHILL |
| Smoke Detectors | 7/24/2020 | Approved | KEITH EDGHILL |
| ELECTRICAL-Final | 7/29/2020 | Approved | KEITH EDGHILL |
| Final | 7/29/2020 | Corrections Issued | KEITH EDGHILL |
| Green Building Final | 7/29/2020 | Corrections Issued | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 7/29/2020 | SGSOV Not Ready | KEITH EDGHILL |
| Final | 8/6/2020 | Corrections Issued | KEITH EDGHILL |
| Green Building Final | 8/6/2020 | Approved | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 8/6/2020 | SGSOV Approved | KEITH EDGHILL |
| Final | 8/17/2020 | Corrections Issued | KEITH EDGHILL |
| Final | 10/7/2020 | OK to Issue CofO | KEITH EDGHILL |