1852 N NORMANDIE AVE 90027
Certificate Information: 1852 N NORMANDIE AVE 90027
- Application / Permit
- 19014-40000-01845
- Plan Check / Job No.
- B19SP00575
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITION AND MAJOR REMODEL TO EXISTING 2-STORY TYPE VB SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 2/22/2021
- Issuing Office
- Current Status
- CofO Issued on 8/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2019 | SERGIO SILVA |
| Corrections Issued | 5/20/2019 | SERGIO SILVA |
| Quality Review Completed | 5/30/2019 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 6/17/2019 | APPLICANT |
| Applicant returned to address corrections | 7/2/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 10/11/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 10/28/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 11/18/2019 | SERGIO SILVA |
| Applicant returned to address corrections | 10/19/2020 | SERGIO SILVA |
| Plan Check Approved | 10/23/2020 | SERGIO SILVA |
| Building Plans Picked Up | 12/10/2020 | APPLICANT |
| Issued | 2/22/2021 | APPLICANT |
| CofO in Progress | 8/9/2023 | JOSEPH MCGARRY |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
| CofO Issued | 8/13/2023 | DEROLD HAUFF |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 7/2/2019 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 7/2/2019 | SERGIO SILVA |
| Miscellaneous | Cleared | 10/11/2019 | SERGIO SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 11/19/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 11/19/2019 | JEREMY CARTER |
| Permit | Cleared | 11/19/2019 | CELINA MORENO |
| Sewer availability | Cleared | 11/19/2019 | CELINA MORENO |
| Trees in Parkway | Cleared | 12/11/2019 | JOHN KIM |
| ZI | Cleared | 7/20/2020 | LINDA LOU |
| Low Impact Development | Cleared | 8/14/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/2/2020 | VICTOR MENDOZA |
| Specific Plan | Cleared | 10/6/2020 | JOE LUCKEY |
| Green Code | Cleared | 10/8/2020 | RICHARD GARCIA |
| Miscellaneous | Cleared | 10/19/2020 | SERGIO SILVA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wong,, Ariv Nathaniel; Lic. No.: C55045 | PO BOX 53364 IRVINE, CA 92619 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/24/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/31/2021 | Partial Approval | JOSEPH MCGARRY |
| Pre-Inspection | 3/31/2021 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/13/2021 | Corrections Issued | ROBERT VORHIS |
| Reinforced Concrete Frame | 4/13/2021 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 4/22/2021 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/22/2021 | Approved | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 4/23/2021 | No Access for Inspection | ELMER BLAND |
| Special/Order Compliance | 4/27/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/7/2021 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 7/14/2021 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/11/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/11/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/12/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/12/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/15/2021 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 9/15/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 9/15/2021 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/14/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/14/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/12/2021 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 11/12/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 11/12/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/23/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 12/2/2021 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 12/10/2021 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 12/10/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 5/27/2022 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 5/27/2022 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 7/14/2022 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 7/14/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/22/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 12/22/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 12/22/2022 | Approved | JOSEPH MCGARRY |
| Final | 6/9/2023 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 6/9/2023 | Approved | JOSEPH MCGARRY |
| Final | 8/2/2023 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Final | 8/8/2023 | OK to Issue CofO | JOSEPH MCGARRY |