2055-2055 1/2 N BARNETT WAY 90032
Certificate Information: 2055-2055 1/2 N BARNETT WAY 90032
- Application / Permit
- 19014-40000-00570
- Plan Check / Job No.
- B19SP00174
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) Two-story addition to the rear of (E) two-story SFD with attached garage to create Accessory Dwelling Unit per SB229 and AB494 on first floor and master bedroom on second with open design to the existing SFD per plans.
- Permit Issued
- Issued on 4/20/2020
- Issuing Office
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2019 | TARIK SAOUD |
| Corrections Issued | 2/19/2019 | TARIK SAOUD |
| Quality Review Completed | 2/28/2019 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 3/19/2019 | APPLICANT |
| Plan Check Approved | 3/11/2020 | TARIK SAOUD |
| Issued | 4/20/2020 | APPLICANT |
| Building Plans Picked Up | 4/21/2020 | APPLICANT |
| CofO in Progress | 3/8/2023 | AMY COLIN |
| CofO Issued | 3/15/2023 | DEROLD HAUFF |
| Permit Finaled | 3/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/20/2019 | ADRIAN SANCHEZ |
| CPC | Cleared | 3/20/2019 | ANNA VAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/27/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 3/27/2019 | GEORGE SUCHAND |
| Disturb/Remove Protected Trees | Cleared | 4/3/2019 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 6/26/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 6/26/2019 | ELAINE LEI |
| Green Code | Cleared | 7/9/2019 | RICHARD GARCIA |
| Private sewage disp. approval | Cleared | 7/16/2019 | PATRICK MISCHLICH |
| BHO/Hillside ordinance | Cleared | 10/10/2019 | ERIK BEASLEY |
| "D" conditions | Cleared | 10/16/2019 | DIANA JIMENEZ |
| "Q" conditions | Cleared | 10/16/2019 | DIANA JIMENEZ |
| Excavation more than 5-ft deep | Cleared | 11/12/2019 | CALOSHA APPROVED |
| Permit | Cleared | 11/22/2019 | THAN WIN |
| BHO/Hillside ordinance | Cleared | 12/26/2019 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 12/26/2019 | TARIK SAOUD |
Contact Information
| Contractor | Gibson Design / Build; Lic. No.: 810077-B | 512 DE SOTO DR HEMET, CA 92543 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| LILIANA PORTILLO, (213) 202-3439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/12/2020 | Partial Approval | ENRIQUE MIRELES |
| Masonry Wall/Backfill | 5/21/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/6/2020 | Partial Approval | ENRIQUE MIRELES |
| Underground Mechanical | 7/6/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/9/2020 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/14/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/14/2020 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/15/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/10/2020 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2020 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/10/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/10/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/26/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 8/26/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 8/26/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/26/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 9/15/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/15/2020 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 9/21/2020 | Approved | COREY HUPP |
| Final | 10/25/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 10/25/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/25/2021 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 10/25/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 3/4/2022 | Corrections Issued | COREY HUPP |
| Green Building Final | 3/4/2022 | Not Ready for Inspection | COREY HUPP |
| Smoke Detectors | 3/4/2022 | Not Ready for Inspection | COREY HUPP |
| Final | 10/27/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Final | 10/27/2022 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 10/27/2022 | Not Ready for Inspection | AMY COLIN |
| Final | 11/30/2022 | Partial Approval | AMY COLIN |
| Green Building Final | 11/30/2022 | Approved | AMY COLIN |
| Smoke Detectors | 11/30/2022 | Approved | AMY COLIN |
| Final | 3/8/2023 | OK to Issue CofO | AMY COLIN |