1740 S AMHERST AVE 90025

Certificate Information: 1740 S AMHERST AVE 90025

Application / Permit
19014-40000-00347
Plan Check / Job No.
B19SP00097
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND ALTERATION TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING.
Permit Issued
Issued on 12/2/2019
Issuing Office
West Los Angeles
Current Status
Issued on 12/2/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/23/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2019 SERGIO SILVA
Corrections Issued 2/25/2019 SERGIO SILVA
Quality Review Completed 3/7/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 3/21/2019 APPLICANT
Green Plans Picked Up 3/21/2019 APPLICANT
Applicant returned to address corrections 7/23/2019 SERGIO SILVA
Plan Check Approved 8/29/2019 SERGIO SILVA
Issued 12/2/2019 LADBS

Permit Application Clearance Information

CPC Cleared 5/23/2019 KIT AWAKUNI
Permit Cleared 5/23/2019 ELENA LOPEZ
Sewer availability Cleared 5/23/2019 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/16/2019 ELAINE LEI
Low Impact Development Cleared 7/16/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 7/16/2019 ELAINE LEI
Trees in Parkway Cleared 8/23/2019 ADRIAN SANCHEZ
Green Code Cleared 8/27/2019 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/31/2019 Partial Inspection RONALD WEBER
Footing/Foundation/Slab 1/3/2020 Approved OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 2/11/2020 Partial Approval KENNETH NAGLE
Underground Mechanical 2/21/2020 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/26/2020 Partial Approval ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 3/23/2020 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 4/17/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 5/5/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 5/7/2020 Partial Approval OGANES TARAKHCHYAN
Sewer 5/7/2020 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/27/2020 Approved OGANES TARAKHCHYAN
HVAC-Rough 5/27/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Special/Order Compliance 6/17/2020 Partial Inspection KENNETH NAGLE
HVAC-Rough 6/18/2020 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/24/2020 Approved OGANES TARAKHCHYAN
Green Building Rough 6/24/2020 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/24/2020 Approved OGANES TARAKHCHYAN
Service/Power Release 7/17/2020 Approved OGANES TARAKHCHYAN
Service/Power Release 7/27/2020 Approved KENNETH NAGLE
Shower Pan 8/12/2020 Approved OGANES TARAKHCHYAN
Pre-Inspection 11/18/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Final 11/22/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 11/22/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Final 11/22/2021 Approved OGANES TARAKHCHYAN