1319 W DON ST 90744
Certificate Information: 1319 W DON ST 90744
- Application / Permit
- 19014-40000-00259
- Plan Check / Job No.
- B19SP00073
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST FLOOR & (N) 2ND FLOOR ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING WITH ATTACHED FRONT GARAGE.
- Permit Issued
- Issued on 2/8/2021
- Issuing Office
- Current Status
- CofO Issued on 8/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2019 | ERWIN PASCUA |
| Corrections Issued | 2/19/2019 | ERWIN PASCUA |
| Quality Review Completed | 2/28/2019 | MARJAN SHENASI |
| Green Plans Picked Up | 4/15/2019 | APPLICANT |
| Building Plans Picked Up | 5/8/2019 | APPLICANT |
| Applicant returned to address corrections | 9/1/2020 | ERWIN PASCUA |
| Applicant returned to address corrections | 9/18/2020 | ERWIN PASCUA |
| Plan Check Approved | 1/15/2021 | ERWIN PASCUA |
| Issued | 2/8/2021 | APPLICANT |
| CofO in Progress | 8/8/2023 | JOHN KLARIN |
| CofO Issued | 8/8/2023 | ANSON MAGLASANG |
| Permit Finaled | 8/8/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Abandoned oil well | Cleared | 4/1/2019 | GILBERT URREA |
| Abandoned oil well approval | Cleared | 4/1/2019 | GILBERT URREA |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 4/1/2019 | GILBERT URREA |
| Sewer availability | Cleared | 4/1/2019 | ELAINE LEI |
| ZI | Cleared | 4/5/2019 | BLAYNE SUTTON-WILLS |
| Miscellaneous | Cleared | 4/9/2019 | LATANYA ROUX |
| Miscellaneous | Cleared | 4/9/2019 | LATANYA ROUX |
| Certificate of Compliance | Cleared | 4/30/2019 | MARC WOERSCHING |
| Green Code | Cleared | 5/31/2019 | ERWIN PASCUA |
| Low Impact Development | Cleared | 8/16/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/16/2019 | JAMES KHO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manlangit,, Vicente Balingasa; Lic. No.: C75499 | 20626 HAYNES ST WINNETKA, CA 91306 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/25/2021 | Partial Inspection | EUGENE CASSIDY |
| Pre-Inspection | 6/10/2021 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 7/7/2021 | Approved | JOHN KLARIN |
| METHANE-Barrier | 7/7/2021 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 7/7/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Partial Approval | EUGENE CASSIDY |
| Insulation | 7/22/2021 | Partial Approval | ANSON MAGLASANG |
| Wood Frame | 7/22/2021 | Partial Approval | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2021 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2021 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 10/15/2021 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 10/15/2021 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/22/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 11/22/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 11/22/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 11/22/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 11/22/2021 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/30/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 11/30/2021 | Corrections Issued | JOHN KLARIN |
| Wood Frame | 12/16/2021 | Approved | JOHN KLARIN |
| Insulation | 12/22/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 1/14/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 1/14/2022 | Partial Approval | ANSON MAGLASANG |
| Shower Pan | 3/29/2022 | Approved | EUGENE CASSIDY |
| Service/Power Release | 4/11/2022 | Corrections Issued | EUGENE CASSIDY |
| Final | 12/5/2022 | Corrections Issued | JOHN KLARIN |
| Pre-Inspection | 12/5/2022 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/22/2023 | Approved | EUGENE CASSIDY |
| Final | 3/22/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 3/22/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/22/2023 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 3/22/2023 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 3/22/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 6/7/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 6/7/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 6/7/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 7/26/2023 | OK to Issue CofO | JOHN KLARIN |
| Green Building Final | 7/26/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 7/26/2023 | Approved | JOHN KLARIN |
| Smoke Detectors | 7/26/2023 | Approved | JOHN KLARIN |