20425 W BALTAR ST 91306

Certificate Information: 20425 W BALTAR ST 91306

Application / Permit
19014-40000-00056
Plan Check / Job No.
B19SP00012
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of and one-story addition to (E) garage to create Accessory Dwelling Unit.
Permit Issued
Issued on 7/17/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2019 APPLICANT
Assigned to Plan Check Engineer 2/1/2019 CHRISTOPHER KOMANCHECK
Corrections Issued 2/1/2019 CHRISTOPHER KOMANCHECK
Green Plans Picked Up 4/11/2019 APPLICANT
Applicant returned to address corrections 12/12/2019 JASON JANGADA
Applicant returned to address corrections 6/10/2020 RICARDO RAMIREZ
Plan Check Approved 7/8/2020 RICARDO RAMIREZ
Building Plans Picked Up 7/13/2020 APPLICANT
Issued 7/17/2020 APPLICANT
CofO in Progress 1/22/2021 HENRY KIM
Permit Finaled 1/26/2021 JOHN JANSON
CofO Issued 1/26/2021 JOHN JANSON
Permit Finaled 1/26/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/29/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 3/29/2019 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 3/29/2019 GEORGE SUCHAND
Permit Cleared 3/29/2019 ADRIAN SANCHEZ
Sewer availability Cleared 3/29/2019 ADRIAN SANCHEZ
Green Code Cleared 11/25/2019 RICHARD GARCIA
Trees in Parkway Cleared 12/2/2019 ADRIAN SANCHEZ
Low Impact Development Cleared 12/3/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 12/3/2019 CELINA MORENO
Construction near power lines Cleared 1/29/2020 RIDWAN HARDY
Construction within easement Cleared 1/29/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/23/2020 Corrections Issued HENRY KIM
Pre-Inspection 7/23/2020 Approved HENRY KIM
PLUMBING-Rough 7/28/2020 Partial Approval HENRY KIM
Underground Mechanical 7/28/2020 Approved HENRY KIM
Footing/Foundation/Slab 8/3/2020 Approved HENRY KIM
Sewer 8/10/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/12/2020 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Corrections Issued HENRY KIM
PLUMBING-Rough 8/14/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Approved HENRY KIM
HVAC-Rough 9/1/2020 Approved HENRY KIM
BUILDING-Rough-Frame 9/3/2020 Approved HENRY KIM
ELECTRICAL-Rough 9/3/2020 Approved HENRY KIM
Green Building Rough 9/3/2020 Approved HENRY KIM
Insulation 9/9/2020 Approved HENRY KIM
Interior/Exterior Lathing 9/9/2020 Approved HENRY KIM
Drywall Nailing 9/14/2020 Approved HENRY KIM
Green Building Final 9/14/2020 Partial Approval HENRY KIM
ELECTRICAL-Final 10/13/2020 Corrections Issued HENRY KIM
Final 10/13/2020 Corrections Issued HENRY KIM
Green Building Final 10/13/2020 Approved HENRY KIM
HVAC-Final 10/13/2020 Corrections Issued HENRY KIM
PLUMBING-Final 10/13/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 10/13/2020 SGSOV Approved HENRY KIM
Smoke Detectors 10/13/2020 Approved HENRY KIM
ELECTRICAL-Final 10/19/2020 Approved HENRY KIM
Final 10/19/2020 Corrections Issued HENRY KIM
HVAC-Final 10/19/2020 Approved HENRY KIM
PLUMBING-Final 10/19/2020 Approved HENRY KIM
Final 12/4/2020 Corrections Issued HENRY KIM
Final 1/22/2021 OK to Issue CofO HENRY KIM