1257 N LAGOON AVE 90744

Certificate Information: 1257 N LAGOON AVE 90744

Application / Permit
19014-40000-00016
Plan Check / Job No.
B19SP00002
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New, one-storyAccessory Dwelling Unit per SB229 and AB494 with attached porch (37'-9" x 22'-0", 775 SF) at the rear of the property. All work per Engineered Design.
Permit Issued
Issued on 7/1/2020
Issuing Office
Current Status
CofO Issued on 1/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2019 APPLICANT
Assigned to Plan Check Engineer 2/1/2019 CHRISTOPHER KOMANCHECK
Corrections Issued 2/1/2019 CHRISTOPHER KOMANCHECK
Green Plans Picked Up 4/3/2019 APPLICANT
Building Plans Picked Up 4/4/2019 APPLICANT
Applicant returned to address corrections 7/8/2019 CHRISTOPHER KOMANCHECK
Plan Check Approved 10/22/2019 CHRISTOPHER KOMANCHECK
Issued 7/1/2020 APPLICANT
CofO in Progress 12/21/2021 ANSON MAGLASANG
Permit Finaled 1/3/2022 DEROLD HAUFF
CofO Issued 1/3/2022 DEROLD HAUFF
Permit Finaled 1/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/18/2019 ALINE MILLER
Sewer availability Cleared 4/18/2019 ALINE MILLER
Hydrant and Access approval Cleared 4/22/2019 GILBERT URREA
ZA Case Cleared 4/22/2019 LATANYA ROUX
ZA Case Cleared 4/22/2019 LATANYA ROUX
Green Code Cleared 5/30/2019 DONALD CRICHLOW
Low Impact Development Cleared 6/20/2019 SEAN SHAHMIRI
Address approval Cleared 7/8/2019 ALINE MILLER
Roof/Waste drainage to street Cleared 7/8/2019 ALINE MILLER
Green Code Cleared 8/19/2019 CHRISTOPHER KOMANCHECK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/17/2020 Approved JOHN KLARIN
METHANE-Barrier 12/17/2020 Approved JOHN KLARIN
METHANE-Subgrade 12/17/2020 Approved JOHN KLARIN
PLUMBING-Rough 1/6/2021 Partial Approval JOHN KLARIN
Insulation 1/7/2021 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 2/8/2021 Partial Approval JOHN KLARIN
Green Building Rough 2/8/2021 Not Ready for Inspection JOHN KLARIN
METHANE-Rough 2/8/2021 Approved JOHN KLARIN
Verify Sprinkler Sign Off 2/8/2021 Not Ready for Inspection JOHN KLARIN
Wood Frame 2/8/2021 Partial Approval JOHN KLARIN
Interior/Exterior Lathing 3/3/2021 Conditional Approval JOHN KLARIN
Rough-Elec/Plmb/HVAC 4/6/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 4/8/2021 Approved JOHN KLARIN
PLUMBING-Rough 4/8/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/15/2021 Approved EUGENE CASSIDY
Green Building Rough 4/15/2021 Approved EUGENE CASSIDY
Insulation 4/15/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 4/15/2021 Approved EUGENE CASSIDY
Wood Frame 4/15/2021 Approved EUGENE CASSIDY
Drywall Nailing 4/23/2021 Approved JOHN KLARIN
Final 10/18/2021 Corrections Issued JOHN KLARIN
Green Building Final 10/18/2021 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV Approved JOHN KLARIN
Service/Power Release 10/18/2021 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 10/18/2021 Approved JOHN KLARIN
Final 12/21/2021 OK to Issue CofO ANSON MAGLASANG
Green Building Final 12/21/2021 Approved ANSON MAGLASANG
Service/Power Release 12/21/2021 Approved ANSON MAGLASANG