9455 W EDEN DR 90210
Certificate Information: 9455 W EDEN DR 90210
- Application / Permit
- 19014-30004-00787
- Plan Check / Job No.
- B21WL02202
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- supplemental ref to pcis# 19014-30000-00787, to rebuild and covered (e) trellis.
- Permit Issued
- Issued on 12/17/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | ALFREDO JARA |
| Corrections Issued | 6/3/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 10/19/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 11/4/2021 | JASON JANGADA |
| Applicant returned to address corrections | 11/5/2021 | JASON JANGADA |
| Applicant returned to address corrections | 12/2/2021 | MANUEL GARCIA |
| Plan Check Approved | 12/8/2021 | JASON JANGADA |
| Issued | 12/17/2021 | APPLICANT |
| Building Plans Picked Up | 12/22/2021 | APPLICANT |
| Permit Finaled | 8/8/2022 | RAUL BARAJAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/15/2021 | KENTON TRINH |
| ZA Case | Cleared | 7/15/2021 | KENTON TRINH |
| ZA Case | Cleared | 7/15/2021 | KENTON TRINH |
| BHO/Hillside ordinance | Cleared | 7/16/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 7/16/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 7/16/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 7/16/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 7/22/2021 | BRIAN MILLER |
| Miscellaneous | Cleared | 8/3/2021 | OLGA AYALA |
| Specific Plan | Cleared | 8/3/2021 | OLGA AYALA |
| Low Impact Development | Cleared | 10/13/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 10/15/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/25/2021 | RAYMOND MUGAMBWA |
Contact Information
| Contractor | Plexus Property U S A; Lic. No.: 1002658-B | 205 S BARRINGTON AVE APT 3 LOS ANGELES, CA 90049 |
| Engineer | Desai,, Anil Thakorbhai; Lic. No.: C24653 | 1530 VIA LOS COYOTES LA HABRA, CA 90631 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12540 DESTINO ST CERRITOS, CA 90703 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/7/2022 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/10/2022 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/27/2022 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 4/27/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/10/2022 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 6/10/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/28/2022 | Approved | RAUL BARAJAS |
| Final | 7/28/2022 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/28/2022 | Approved | RAUL BARAJAS |
| Green Building Final | 7/28/2022 | Approved | RAUL BARAJAS |
| Smoke Detectors | 7/28/2022 | Approved | RAUL BARAJAS |
| Final | 8/8/2022 | Permit Finaled | RAUL BARAJAS |