6112 W 6TH ST 90048

Certificate Information: 6112 W 6TH ST 90048

Application / Permit
19014-30002-05125
Plan Check / Job No.
B21WL02554
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental ref to pcis # 19014-30000-05125, to add (89 sf sf) to the first floor with roof deck above to add a bedroom and bathroom at 1st floor and extend the (e) balcony at 2nd floor and revise floor plan layout
Permit Issued
Issued on 6/13/2022
Issuing Office
Current Status
Permit Finaled on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2021 APPLICANT
Assigned to Plan Check Engineer 6/25/2021 REZA HAGHIGHAT
Corrections Issued 6/28/2021 REZA HAGHIGHAT
Quality Review Completed 7/7/2021 TARIK SAOUD
Applicant returned to address corrections 1/21/2022 REZA HAGHIGHAT
Applicant returned to address corrections 3/1/2022 REZA HAGHIGHAT
Applicant returned to address corrections 3/4/2022 REZA HAGHIGHAT
Applicant returned to address corrections 3/25/2022 REZA HAGHIGHAT
Plan Check Approved 5/7/2022 REZA HAGHIGHAT
Issued 6/13/2022 APPLICANT
Building Plans Picked Up 6/15/2022 APPLICANT
Permit Finaled 12/17/2024 RUBEN PEREZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/16/2021 CINDY QI
Roof/Waste drainage to street Cleared 11/16/2021 CINDY QI
Sewer availability Cleared 11/16/2021 CINDY QI
CPC Cleared 11/23/2021 MAXFIELD VERMY

Contact Information

Contractor Midland Contractors Inc; Lic. No.: 719159-A P O BOX 8312      VAN NUYS, CA 91409
Contractor Midland Contractors Inc; Lic. No.: 719159-B P O BOX 8312      VAN NUYS, CA 91409
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/8/2022 Conditional Approval JOEL WILLIAMS
Footing/Foundation/Slab 9/14/2022 Partial Approval HAGOP BADOSSIAN
METHANE-Barrier 9/14/2022 Conditional Approval HAGOP BADOSSIAN
METHANE-Subgrade 9/14/2022 Conditional Approval HAGOP BADOSSIAN
Footing/Foundation/Slab 9/20/2022 Partial Approval HAGOP BADOSSIAN
METHANE-Barrier 9/20/2022 Partial Approval HAGOP BADOSSIAN
METHANE-Subgrade 9/20/2022 Partial Approval HAGOP BADOSSIAN
BUILDING-Rough-Frame 12/17/2024 Approved RUBEN PEREZ
Drywall Nailing 12/17/2024 Approved RUBEN PEREZ
Final 12/17/2024 Permit Finaled RUBEN PEREZ
Footing/Foundation/Slab 12/17/2024 Approved RUBEN PEREZ
Green Building Final 12/17/2024 Approved RUBEN PEREZ
Green Building Rough 12/17/2024 Approved RUBEN PEREZ
METHANE-Barrier 12/17/2024 Approved RUBEN PEREZ
METHANE-Final 12/17/2024 Approved RUBEN PEREZ
METHANE-Rough 12/17/2024 Approved RUBEN PEREZ
METHANE-Subgrade 12/17/2024 Approved RUBEN PEREZ
Smoke Detectors 12/17/2024 Approved RUBEN PEREZ