6112 W 6TH ST 90048
Certificate Information: 6112 W 6TH ST 90048
- Application / Permit
- 19014-30002-05125
- Plan Check / Job No.
- B21WL02554
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental ref to pcis # 19014-30000-05125, to add (89 sf sf) to the first floor with roof deck above to add a bedroom and bathroom at 1st floor and extend the (e) balcony at 2nd floor and revise floor plan layout
- Permit Issued
- Issued on 6/13/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/25/2021 | REZA HAGHIGHAT |
| Corrections Issued | 6/28/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 7/7/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 1/21/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 3/1/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 3/4/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 3/25/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 5/7/2022 | REZA HAGHIGHAT |
| Issued | 6/13/2022 | APPLICANT |
| Building Plans Picked Up | 6/15/2022 | APPLICANT |
| Permit Finaled | 12/17/2024 | RUBEN PEREZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2021 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 11/16/2021 | CINDY QI |
| Sewer availability | Cleared | 11/16/2021 | CINDY QI |
| CPC | Cleared | 11/23/2021 | MAXFIELD VERMY |
Contact Information
| Contractor | Midland Contractors Inc; Lic. No.: 719159-A | P O BOX 8312 VAN NUYS, CA 91409 |
| Contractor | Midland Contractors Inc; Lic. No.: 719159-B | P O BOX 8312 VAN NUYS, CA 91409 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/8/2022 | Conditional Approval | JOEL WILLIAMS |
| Footing/Foundation/Slab | 9/14/2022 | Partial Approval | HAGOP BADOSSIAN |
| METHANE-Barrier | 9/14/2022 | Conditional Approval | HAGOP BADOSSIAN |
| METHANE-Subgrade | 9/14/2022 | Conditional Approval | HAGOP BADOSSIAN |
| Footing/Foundation/Slab | 9/20/2022 | Partial Approval | HAGOP BADOSSIAN |
| METHANE-Barrier | 9/20/2022 | Partial Approval | HAGOP BADOSSIAN |
| METHANE-Subgrade | 9/20/2022 | Partial Approval | HAGOP BADOSSIAN |
| BUILDING-Rough-Frame | 12/17/2024 | Approved | RUBEN PEREZ |
| Drywall Nailing | 12/17/2024 | Approved | RUBEN PEREZ |
| Final | 12/17/2024 | Permit Finaled | RUBEN PEREZ |
| Footing/Foundation/Slab | 12/17/2024 | Approved | RUBEN PEREZ |
| Green Building Final | 12/17/2024 | Approved | RUBEN PEREZ |
| Green Building Rough | 12/17/2024 | Approved | RUBEN PEREZ |
| METHANE-Barrier | 12/17/2024 | Approved | RUBEN PEREZ |
| METHANE-Final | 12/17/2024 | Approved | RUBEN PEREZ |
| METHANE-Rough | 12/17/2024 | Approved | RUBEN PEREZ |
| METHANE-Subgrade | 12/17/2024 | Approved | RUBEN PEREZ |
| Smoke Detectors | 12/17/2024 | Approved | RUBEN PEREZ |