1230 N LA COLLINA DR 90069

Certificate Information: 1230 N LA COLLINA DR 90069

Application / Permit
19014-30002-03562
Plan Check / Job No.
B21WL02039
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
supplemental ref to pcis # 19014-30000-03562, for structural revisions and addition
Permit Issued
Issued on 11/22/2021
Issuing Office
Current Status
Permit Finaled on 8/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 SERGIO SILVA
Corrections Issued 6/10/2021 SERGIO SILVA
Quality Review Completed 6/21/2021 TARIK SAOUD
Applicant returned to address corrections 8/16/2021 SERGIO SILVA
Applicant returned to address corrections 9/8/2021 SERGIO SILVA
Applicant returned to address corrections 11/17/2021 SERGIO SILVA
Plan Check Approved 11/18/2021 SERGIO SILVA
Issued 11/22/2021 APPLICANT
Building Plans Picked Up 11/23/2021 APPLICANT
Permit Finaled 8/18/2023 RAUL BARAJAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/30/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 7/30/2021 STEVE MELGAR
Permit Cleared 7/30/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 7/30/2021 STEVE MELGAR
Sewer availability Cleared 7/30/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 8/2/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/2/2021 STEVE MELGAR
Miscellaneous Cleared 8/2/2021 LOUIS ORTEGA
Miscellaneous Cleared 8/2/2021 LOUIS ORTEGA
Miscellaneous Cleared 8/2/2021 LOUIS ORTEGA
Miscellaneous Cleared 8/2/2021 LOUIS ORTEGA
ZA Case Cleared 8/2/2021 LOUIS ORTEGA
Excavation more than 5-ft deep Cleared 9/8/2021 CALOSHA APPROVED
Green Code Cleared 9/8/2021 SERGIO SILVA
Trees in Parkway Cleared 9/8/2021 JOHN KIM
Hydrant and Access approval Cleared 9/19/2021 JOHN CONNEALLY
Low Impact Development Cleared 10/20/2021 TA ANH

Contact Information

Architect Peck,, Christopher M; Lic. No.: C27316 C.M. PECK CONSULTING   25 S. EL MOLINO AVE    PASADENA, CA 911012023
Contractor J R C Group Inc; Lic. No.: 980658-B 8981 SUNSET BLVD STE 505      LOS ANGELES, CA 90069
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Peck,, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/21/2021 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 12/21/2021 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 1/6/2022 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 1/13/2022 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 1/25/2022 Approved RAUL BARAJAS
Reinforced Concrete Frame 2/9/2022 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 2/16/2022 Partial Approval RAUL BARAJAS
PLUMBING-Rough 2/16/2022 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/22/2022 Partial Approval RAUL BARAJAS
Underground Mechanical 3/2/2022 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 3/3/2022 Approved RAUL BARAJAS
Reinforced Masonry Frame 3/15/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/18/2022 Conditional Approval SCOTT FINNILA
Deputy Steel/Welding 3/25/2022 Conditional Approval RAUL BARAJAS
Reinforced Concrete Frame 4/4/2022 Approved RAUL BARAJAS
Reinforced Masonry Frame 4/4/2022 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 4/14/2022 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 4/14/2022 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval RAUL BARAJAS
Reinforced Concrete Frame 4/26/2022 Partial Approval RAUL BARAJAS
Structural Steel Frame 4/29/2022 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Partial Approval RUBEN SALAS
Underground Mechanical 5/18/2022 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/24/2022 Partial Approval RAUL BARAJAS
Underground Mechanical 5/24/2022 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 5/31/2022 Approved RAUL BARAJAS
Gas Test 6/23/2022 Approved RAUL BARAJAS
Reinforced Concrete Frame 6/23/2022 Not Ready for Inspection RAUL BARAJAS
Special/Order Compliance 7/11/2022 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/29/2022 Approved RAUL BARAJAS
PLUMBING-Rough 8/16/2022 Partial Inspection RAUL BARAJAS
Wood Frame 8/29/2022 Partial Approval RAUL BARAJAS
Underground Mechanical 9/12/2022 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 9/19/2022 Partial Approval RAUL BARAJAS
HVAC-Rough 9/19/2022 Not Ready for Inspection RAUL BARAJAS
Shower Pan 9/19/2022 Approved RAUL BARAJAS
ELECTRICAL-Rough 9/21/2022 Partial Approval RAUL BARAJAS
HVAC-Rough 9/21/2022 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 9/21/2022 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 9/27/2022 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 10/13/2022 Partial Approval RAUL BARAJAS
HVAC-Rough 10/13/2022 Partial Approval RAUL BARAJAS
PLUMBING-Rough 10/13/2022 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 10/19/2022 Partial Inspection RAUL BARAJAS
PLUMBING-Rough 10/19/2022 Partial Inspection RAUL BARAJAS
Interior/Exterior Lathing 10/27/2022 Not Ready for Inspection RAUL BARAJAS
Rough-Elec/Plmb/HVAC 10/27/2022 Conditional Approval RAUL BARAJAS
Interior/Exterior Lathing 11/2/2022 Approved RAUL BARAJAS
Insulation 11/10/2022 Approved RAUL BARAJAS
Underground Mechanical 11/10/2022 Approved RAUL BARAJAS
Drywall Nailing 11/18/2022 Partial Approval RAUL BARAJAS
Green Building Rough 11/18/2022 Approved RAUL BARAJAS
Interior/Exterior Lathing 11/18/2022 Approved RAUL BARAJAS
Shower Pan 12/5/2022 Approved RAUL BARAJAS
Interior/Exterior Lathing 1/12/2023 Not Ready for Inspection JULIAN AMAYA
Interior/Exterior Lathing 1/17/2023 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/26/2023 Corrections Issued RAUL BARAJAS
Shower Pan 1/26/2023 Approved RAUL BARAJAS
Sewer 2/16/2023 Partial Approval RAUL BARAJAS
Underground Mechanical 2/22/2023 Partial Approval RAUL BARAJAS
Shower Pan 3/1/2023 Approved RAUL BARAJAS
ELECTRICAL-Rough 3/7/2023 Partial Approval RAUL BARAJAS
PLUMBING-Rough 3/7/2023 Approved RAUL BARAJAS
ELECTRICAL-Rough 3/30/2023 Conditional Approval RAUL BARAJAS
HVAC-Rough 3/30/2023 Conditional Approval RAUL BARAJAS
PLUMBING-Rough 3/30/2023 Conditional Approval RAUL BARAJAS
Gas Test 5/4/2023 Approved RAUL BARAJAS
Service/Power Release 6/5/2023 Corrections Issued STUART CHAPMAN
Service/Power Release 6/7/2023 Partial Inspection RAUL BARAJAS
Service/Power Release 6/22/2023 Approved RAUL BARAJAS
Underground Mechanical 7/31/2023 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 8/7/2023 Approved RAUL BARAJAS
Drywall Nailing 8/7/2023 Approved RAUL BARAJAS
Final 8/7/2023 Partial Inspection RAUL BARAJAS
Green Building Final 8/7/2023 Not Ready for Inspection RAUL BARAJAS
Smoke Detectors 8/7/2023 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/7/2023 Approved RAUL BARAJAS
Final 8/18/2023 Permit Finaled RAUL BARAJAS
Green Building Final 8/18/2023 Approved RAUL BARAJAS
Smoke Detectors 8/18/2023 Approved RAUL BARAJAS