630 N NIMES ROAD 90077

Certificate Information: 630 N NIMES ROAD 90077

Application / Permit
19014-30002-00466
Plan Check / Job No.
B20WL01167
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental to permit 19014-30000-00466 to revise arch & structural plans. no change in floor area and no site plan changes. change fire sprinklers to NFPA13D
Permit Issued
Issued on 7/16/2020
Issuing Office
Current Status
Permit Finaled on 10/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2020 APPLICANT
Assigned to Plan Check Engineer 3/25/2020 TARIK SAOUD
Green Plans Picked Up 3/25/2020 APPLICANT
Corrections Issued 4/8/2020 TARIK SAOUD
Quality Review Completed 4/9/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 7/10/2020 TARIK SAOUD
No Progress 7/10/2020 TARIK SAOUD
Plan Check Approved 7/13/2020 TARIK SAOUD
Issued 7/16/2020 APPLICANT
Building Plans Picked Up 9/16/2020 APPLICANT
Permit Finaled 10/30/2024 CHRISTOPHER WILSON

Permit Application Clearance Information

Green Code Cleared 3/21/2020 DONALD CRICHLOW
Eng Process Fee Ord 176,300 Cleared 4/14/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 4/14/2020 DINAH GARIN

Contact Information

Contractor Scg Development Group Inc; Lic. No.: 1016344-B 1811 MICHELTORENA STREET      LOS ANGELES, CA 90026
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Garcia,, Lionel Jesus; Lic. No.: C58475 24702 NARBONNE AVE      LOMITA, CA 90717
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/5/2020 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/14/2020 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/25/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/16/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 2/16/2021 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 2/17/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/22/2021 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 2/23/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 2/26/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/10/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/12/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/31/2021 Partial Approval ANTHONY MCDOWALL
Interior/Exterior Lathing 4/6/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 4/14/2021 Partial Approval ALIZAH MAYAGOITIA
Pre-Inspection 4/14/2021 Partial Inspection JESUS PINEDA
PLUMBING-Rough 4/16/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 4/23/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/12/2022 Approved CHRISTOPHER WILSON
Footing/Foundation/Slab 9/12/2022 Approved CHRISTOPHER WILSON
Grounding or Bonding 9/12/2022 Not Ready for Inspection CHRISTOPHER WILSON