1415 S CRESTVIEW CT 90024

Certificate Information: 1415 S CRESTVIEW CT 90024

Application / Permit
19014-30001-06992
Plan Check / Job No.
B20WL04656
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental to pcis # 19014-30000-06992, for 2nd story addition to (E) SFD
Permit Issued
Issued on 2/4/2021
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 3/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 ALFREDO JARA
Corrections Issued 11/4/2020 ALFREDO JARA
Quality Review Completed 11/13/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/19/2021 ALFREDO JARA
Building Plans Picked Up 1/29/2021 APPLICANT
Issued 2/4/2021 APPLICANT
Permit Finaled 3/9/2024 MICHAEL PELHAM

Permit Application Clearance Information

Low Impact Development Cleared 12/2/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/5/2021 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 1/6/2021 TRACY TATE
Sewer availability Cleared 1/6/2021 TRACY TATE

Contact Information

Contractor Owner-Builder       ,
Engineer Khazra,, Afshin; Lic. No.: C50250 22855 PAUL REVERE DR      CALABASAS, CA 91302

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/25/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 3/2/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 3/2/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 3/2/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 3/2/2021 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 3/3/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 3/15/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Partial Approval ANTHONY MCDOWALL
ELECTRICAL-Final 2/9/2023 Corrections Issued STEPHANIE SWANSON
Final 2/9/2023 Corrections Issued STEPHANIE SWANSON
Final 2/13/2023 Partial Inspection STEPHANIE SWANSON