530 S LORING AVE 90024

Certificate Information: 530 S LORING AVE 90024

Application / Permit
19014-30001-06981
Plan Check / Job No.
B20WL03852
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental ref to pcis # 1914-30000-06981, to increase addition size, revise changes due to field conditions, raise second floor ceiling height and revise structural plans and calculation, and revise permit valuation from $200,000 to $430,000 and capture additional permit fee.
Permit Issued
Issued on 11/30/2020
Issuing Office
West Los Angeles
Current Status
Issued on 11/30/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/3/2020 APPLICANT
Assigned to Plan Check Engineer 9/9/2020 KAVIAN REFAHI
Corrections Issued 9/14/2020 KAVIAN REFAHI
Quality Review Completed 9/18/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/18/2020 KAVIAN REFAHI
Building Plans Picked Up 11/19/2020 APPLICANT
Plan Check Approved 11/23/2020 KAVIAN REFAHI
Issued 11/30/2020 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/21/2020 HISASHI KOBAYAKAWA
Low Impact Development Cleared 10/29/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/2/2020 HISASHI KOBAYAKAWA

Contact Information

Contractor United Remodeling Construction Inc; Lic. No.: 813590-B 4924 BALBOA BLVD #447      ENCINO, CA 91316
Engineer Enayat,, Simhaee; Lic. No.: C37206 1332 S ST JOSEPH PL      LOS ANGELES, CA 90015

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/1/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/9/2020 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 12/23/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 12/23/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/21/2021 Not Ready for Inspection ANTHONY MCDOWALL
ELECTRICAL-Rough 4/21/2021 Approved ANTHONY MCDOWALL
Green Building Rough 4/21/2021 Not Ready for Inspection ANTHONY MCDOWALL
HVAC-Rough 4/21/2021 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Rough 4/21/2021 Not Ready for Inspection ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 4/23/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/23/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/26/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 4/26/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 4/26/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/25/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/7/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 6/7/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 6/7/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/7/2021 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 6/17/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 6/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Shower Pan 6/17/2021 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/21/2021 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 6/21/2021 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 6/28/2021 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 4/4/2022 Approved BRENDAN LOONEY
HVAC-Final 4/4/2022 Approved BRENDAN LOONEY