1028 N VILLA GROVE DR 90272
Certificate Information: 1028 N VILLA GROVE DR 90272
- Application / Permit
- 19014-30001-06901
- Plan Check / Job No.
- B20WL05567
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental permit to # 19014-30000-06901 to reduce the size of 2nd floor addition
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 9/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | REZA HAGHIGHAT |
| Corrections Issued | 1/11/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 1/21/2021 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
| Plan Check Approved | 2/26/2021 | REZA HAGHIGHAT |
| Issued | 3/19/2021 | APPLICANT |
| Permit Finaled | 9/30/2021 | JOHN KIDWELL |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/10/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/23/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2021 | DINAH GARIN |
Contact Information
| Contractor | Paramount Contractors Inc; Lic. No.: 978411-B | 108 SOUTH HELBERTA AVE #A REDONDO BEACH, CA 90277 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/10/2021 | Conditional Approval | ROBERT SHELLY |
| Footing/Foundation/Slab | 5/14/2021 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/7/2021 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 6/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 6/7/2021 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/14/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 6/14/2021 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 6/14/2021 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 6/14/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2021 | Conditional Approval | JOHN KIDWELL |
| HVAC-Rough | 6/17/2021 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 6/17/2021 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/2/2021 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 7/6/2021 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 7/6/2021 | Approved | JOHN KIDWELL |
| Green Building Rough | 7/6/2021 | Approved | JOHN KIDWELL |
| HVAC-Rough | 7/6/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 7/6/2021 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 7/6/2021 | Approved | JOHN KIDWELL |
| Wood Frame | 7/6/2021 | Approved | JOHN KIDWELL |
| Insulation | 7/8/2021 | Approved | JACK MATTILLO |
| Interior/Exterior Lathing | 7/8/2021 | Approved | JACK MATTILLO |
| Shower Pan | 7/8/2021 | Approved | JACK MATTILLO |
| Interior/Exterior Lathing | 7/13/2021 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 7/19/2021 | Approved | PIERRE VEGA |
| ELECTRICAL-Final | 8/20/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 8/20/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 8/20/2021 | Not Ready for Inspection | JUAN VALENZUELA |