Supplemental permit to 19014-30000-04900, for 106 SF addition and (n) decks. See comments.
Permit Issued
Issued on 5/4/2021
Issuing Office
Current Status
Permit Finaled on 8/18/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/20/2020 APPLICANT
Assigned to Plan Check Engineer 10/20/2020 KAVIAN REFAHI
Corrections Issued 10/20/2020 KAVIAN REFAHI
Applicant returned to address corrections 11/24/2020 ALFREDO JARA
Applicant returned to address corrections 12/23/2020 JASON JANGADA
Building Plans Picked Up 12/24/2020 APPLICANT
Plan Check Approved 1/14/2021 JASON JANGADA
Issued 5/4/2021 APPLICANT
Permit Finaled 8/17/2022 STUART CHAPMAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/18/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 11/18/2020 WALLIE JONG

Contact Information

Architect Bowker,, Adney Stephen; Lic. No.: C31512 4606 W JEFFERSON BLVD      LOS ANGELES, CA 90016
Contractor Azure Construction Inc; Lic. No.: 1058246-B 3877 GRAND VIEW BLVD STE 200      LOS ANGELES, CA 90066
Engineer Ghazlani,, Andy A; Lic. No.: C60867 1021 E CARSON ST 5      LONG BEACH, CA 90807

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/25/2021 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Approval RICHARD STEINBACH
BUILDING-Rough-Frame 8/16/2021 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 8/16/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 8/16/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 8/16/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 8/16/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 10/5/2021 Approved STUART CHAPMAN
HVAC-Rough 10/5/2021 Approved STUART CHAPMAN
PLUMBING-Rough 10/5/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 11/4/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 5/31/2022 Approved STUART CHAPMAN
Final 5/31/2022 Corrections Issued STUART CHAPMAN
Green Building Final 5/31/2022 Approved STUART CHAPMAN
Green Building Rough 5/31/2022 Approved STUART CHAPMAN
Smoke Detectors 5/31/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 6/3/2022 Approved STUART CHAPMAN
HVAC-Final 6/3/2022 Approved STUART CHAPMAN
PLUMBING-Final 6/3/2022 Approved STUART CHAPMAN
Final 8/17/2022 Permit Finaled STUART CHAPMAN
Smoke Detectors 8/17/2022 Approved STUART CHAPMAN