480 N ARBRAMAR AVE 90272
Certificate Information: 480 N ARBRAMAR AVE 90272
- Application / Permit
- 19014-30000-07249
- Plan Check / Job No.
- B19WL07422
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION OF 2ND FLOOR AND ATTACHED GARAGE TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 12/1/2021
- Issuing Office
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | SERGIO SILVA |
| Corrections Issued | 3/3/2020 | SERGIO SILVA |
| Quality Review Completed | 3/12/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 3/20/2020 | APPLICANT |
| Applicant returned to address corrections | 5/13/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 6/17/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 7/14/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 9/23/2021 | SERGIO SILVA |
| Plan Check Approved | 10/6/2021 | SERGIO SILVA |
| Issued | 12/1/2021 | APPLICANT |
| Building Plans Picked Up | 12/2/2021 | APPLICANT |
| CofO in Progress | 10/31/2024 | EVAN COOPER |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
| CofO Issued | 11/12/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Coastal Zone | Cleared | 7/13/2021 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 7/13/2021 | DENZEL HENDERSON |
| GPI Written Notices | Cleared | 7/14/2021 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 7/14/2021 | SERGIO SILVA |
| Low Impact Development | Cleared | 9/2/2021 | SUNG JOON WON |
| Permit | Cleared | 9/2/2021 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2021 | CATHERINE ADROVER |
| Sewer availability | Cleared | 9/7/2021 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 9/10/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 9/13/2021 | CATHERINE ADROVER |
| Trees in Parkway | Cleared | 9/22/2021 | ADRIAN SANCHEZ |
| Green Code | Cleared | 10/6/2021 | RICHARD GARCIA |
Contact Information
| Architect | Geller-Seibel,, Rhonda E; Lic. No.: C26598 | 956 CHATTANOOGA AVENUE PACIFIC PALISADES, CA 90272 |
| Contractor | G C Aquascape; Lic. No.: 711587-B | 1903 CALIFORNIA AVENUE SANTA MONICA, CA 90403 |
| Engineer | Azarmy,, Cyrus; Lic. No.: L9404 | 4402 CHARLEMONT AVE WOODLAND HILLS, CA 91364 |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: C50989 | 4930 READ RD MOORPARK, CA 93021 |
| Engineer | Silverman,, David Isaac; Lic. No.: C58650 | 22837 VENTURA BLVD SUITE 100 WOODLAND HILLS, CA 91364 |
| Landscape Architect | Freedman,, Zack David; Lic. No.: LA5582 | 232 LINNIE CANAL VENICE, CA 90291 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/5/2022 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 4/11/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 4/15/2022 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 4/21/2022 | Conditional Approval | ANDREW NAVE |
| Underground Mechanical | 4/22/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 5/4/2022 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 5/5/2022 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/18/2022 | Partial Approval | ANDREW NAVE |
| Green Building Rough | 5/18/2022 | Not Ready for Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2022 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 5/23/2022 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 12/22/2022 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 12/30/2022 | Approved | BRENDAN LOONEY |
| Special/Order Compliance | 12/30/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 1/3/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 1/23/2023 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 2/17/2023 | Conditional Approval | BRENDAN LOONEY |
| Green Building Rough | 2/17/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 2/17/2023 | Approved | BRENDAN LOONEY |
| Insulation | 3/8/2023 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 3/8/2023 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 4/5/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 4/12/2023 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 6/6/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 7/26/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 8/22/2023 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Final | 11/1/2023 | Approved | EVAN COOPER |
| Service/Power Release | 11/1/2023 | Approved | EVAN COOPER |
| HVAC-Final | 11/29/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 12/1/2023 | Approved | EVAN COOPER |
| Final | 1/18/2024 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 1/18/2024 | Approved | EVAN COOPER |
| Green Building Final | 1/18/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 1/18/2024 | Approved | EVAN COOPER |
| Final | 10/31/2024 | OK to Issue CofO | EVAN COOPER |