9011 W ALTO CEDRO DR 90210
Certificate Information: 9011 W ALTO CEDRO DR 90210
- Application / Permit
- 19014-30000-07244
- Plan Check / Job No.
- B19WL07417
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTEND 2ND FLOOR OVER SINGLE STORY PORTION OF A 2-STORY SFD.
- Permit Issued
- Issued on 2/28/2021
- Issuing Office
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 1/22/2020 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 1/31/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 11/19/2020 | APPLICANT |
| Applicant returned to address corrections | 1/6/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 1/8/2021 | JAHANSHAH POURHASSAN |
| Issued | 2/28/2021 | APPLICANT |
| Building Plans Picked Up | 3/1/2021 | APPLICANT |
| CofO in Progress | 8/22/2022 | RAUL BARAJAS |
| Permit Finaled | 10/22/2022 | DEROLD HAUFF |
| CofO Issued | 10/22/2022 | DEROLD HAUFF |
| Permit Finaled | 10/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/8/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2020 | DINAH GARIN |
| Sewer availability | Cleared | 9/29/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 10/22/2020 | MITESH PATEL |
| Private street | Cleared | 12/1/2020 | LAUREN PADICK |
| ZI | Cleared | 12/1/2020 | LAUREN PADICK |
| Specific Plan | Cleared | 12/29/2020 | LAUREN PADICK |
| GPI Written Notices | Cleared | 1/6/2021 | JAHANSHAH POURHASSAN |
| Grading Pre-Inspection | Cleared | 1/6/2021 | JAHANSHAH POURHASSAN |
Contact Information
| Contractor | Williams Craig R Construction Inc; Lic. No.: 479539-B | 9100 WILSHIRE BLVD STE 503E BEVERLY HILLS, CA 90212 |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
| Engineer | Nzeogu,, Godfrey Iheanacho; Lic. No.: C61921 | 1507 EAST GLADWICK ST CARSON, CA 90746 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/25/2021 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/30/2021 | Approved | RAUL BARAJAS |
| Deputy Wood Construction | 5/6/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2021 | Approved | RAUL BARAJAS |
| Wood Frame | 5/27/2021 | Approved | RAUL BARAJAS |
| Deputy Wood Construction | 6/24/2021 | Conditional Approval | JOHN HAMILTON |
| PLUMBING-Rough | 7/13/2021 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Partial Approval | RICHARD STEINBACH |
| HVAC-Rough | 8/12/2021 | Corrections Issued | RICHARD STEINBACH |
| ELECTRICAL-Rough | 9/13/2021 | Corrections Issued | RICHARD STEINBACH |
| ELECTRICAL-Rough | 9/16/2021 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 9/16/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| HVAC-Rough | 9/22/2021 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 11/16/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 11/16/2021 | Approved | STUART CHAPMAN |
| Wood Frame | 11/16/2021 | Approved | STUART CHAPMAN |
| Insulation | 1/11/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 1/24/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 2/17/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 2/17/2022 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 2/28/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 7/11/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 7/11/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 7/11/2022 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 7/11/2022 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 7/11/2022 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 7/11/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 7/12/2022 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 7/12/2022 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 7/12/2022 | Approved | RAUL BARAJAS |
| Final | 8/15/2022 | Conditional Approval | RAUL BARAJAS |
| Green Building Final | 8/15/2022 | Approved | RAUL BARAJAS |