2852 S BURKSHIRE AVE 90064

Certificate Information: 2852 S BURKSHIRE AVE 90064

Application / Permit
19014-30000-07240
Plan Check / Job No.
B19WL07412
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition/remodel to (e) 1-story SFD. Per engineering design.
Permit Issued
Issued on 6/18/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 ALFREDO JARA
Corrections Issued 1/10/2020 ALFREDO JARA
Plan Check Approved 6/3/2020 ALFREDO JARA
Issued 6/18/2020 LADBS
Building Plans Picked Up 6/18/2020 APPLICANT
CofO in Progress 5/11/2021 EVAN COOPER
Permit Finaled 5/20/2021 KENNETH NAGLE
CofO Issued 5/20/2021 KENNETH NAGLE
Permit Finaled 5/20/2021 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/18/2020 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 2/18/2020 ANTHONY MAINEZ
Sewer availability Cleared 2/18/2020 ANTHONY MAINEZ

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Ground Up Builders And Design Inc; Lic. No.: 911849-B 14545 VICTORY BLVD STE 601      VAN NUYS, CA 91411

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/8/2020 Partial Approval JUSTIN CURTIS
Reinforced Concrete Frame 7/22/2020 Conditional Approval JUSTIN CURTIS
BUILDING-Rough-Frame 8/28/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 8/28/2020 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/21/2020 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 9/21/2020 Approved OGANES TARAKHCHYAN
Pre-Inspection 10/7/2020 Approved EVAN COOPER
Shower Pan 10/7/2020 Approved EVAN COOPER
Insulation 10/22/2020 Approved EVAN COOPER
Interior/Exterior Lathing 10/22/2020 Approved EVAN COOPER
Drywall Nailing 10/28/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 1/11/2021 Approved EVAN COOPER
Final 1/11/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 1/11/2021 Approved EVAN COOPER
Green Building Final 1/11/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/11/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 1/11/2021 Approved EVAN COOPER
Final 3/30/2021 Partial Inspection KENNETH NAGLE
Final 4/8/2021 Corrections Issued EVAN COOPER
ELECTRICAL-Final 5/11/2021 Approved EVAN COOPER
Final 5/11/2021 OK to Issue CofO EVAN COOPER
HVAC-Final 5/11/2021 Approved EVAN COOPER
PLUMBING-Final 5/11/2021 Approved EVAN COOPER